Scaffolding calculator

Work out how many bays, levels, frames and planks of frame scaffolding a wall needs, and what the rental will cost.

Updated on
Your inputs
ft

Value out of range

ft

Value out of range

ft

Value out of range

ft

Value out of range

Value out of range

$

Value out of range

Value out of range

Results

Bays

6

Levels

3

End frames

21

Planks if every level is decked
36
Height of the top platform
19.5 ft
Rental cost
$360

Frame scaffolding is the usual choice for painting, siding, masonry or window work on a house. It is built from bays (the length between two frames) stacked in levels (the height of one frame). Knowing the number of bays and levels gives the frames, planks and rental cost.

How the calculation works

  • Bays = wall length ÷ bay length, rounded up
  • Levels = height of the working platform ÷ frame height, rounded up
  • End frames = (bays + 1) × levels
  • Planks = bays × levels × planks per bay, if every level is decked
  • Rental = bays × levels × weekly rate × weeks

Standard frames in the United States are 5 ft wide and 5 ft or 6 ft 4 in tall (walk-through frames are about 6.5 ft), joined by cross braces that set bays of 7 ft (also 5, 8 or 10 ft).

Example

To work on a 40 ft wall from a platform at 18 ft, you need 6 bays of 7 ft and 3 levels of 6.5 ft frames. That is 21 end frames and 36 planks if every level is decked with two planks per bay. The top platform ends up at 19.5 ft. At $10 per bay and level per week, two weeks of rental cost about $360.

What else to order

  • Cross braces: two per bay per level (one on each side).
  • Base plates or screw jacks: one per leg, plus mudsills on soft ground.
  • Guardrails, midrails and toeboards on every working platform, and on the ends.
  • Ties to the building, as OSHA and the manufacturer specify: the first at a height of 4 times the base width, then at least every 26 ft vertically for frames wider than 3 ft and every 30 ft horizontally.
  • Outriggers if the tower is narrow compared with its height.
  • An access ladder or stair tower.

Safety rules

OSHA requires fall protection, usually guardrails, on scaffolds more than 10 ft above a lower level, and scaffolds must be erected, moved and dismantled under the supervision of a competent person. Platforms must be fully planked, and the scaffold must support its own weight plus four times the intended load. Keep at least 10 ft from overhead power lines.

For one-day jobs on a single story, a ladder or a mobile tower may be safer and cheaper.

Frequently asked questions

How many scaffold frames do I need?

One more than the number of bays, multiplied by the number of levels.

How tall is a scaffold frame?

Common frames are 5 ft or 6 ft 4 in tall, with walk-through frames about 6.5 ft.

When does scaffolding need guardrails?

OSHA requires fall protection on scaffolds more than 10 feet above a lower level.

How much does scaffolding rental cost?

It varies by area; ask suppliers for a price per frame or per bay and level per week.

Was this calculator helpful?

Thanks for your feedback!

Results are estimates provided for information purposes. They do not replace professional advice.