Traffic signal cycle length calculator: Webster cycle and green split

Enter the critical flows of three phases, the saturation flow and the lost time to get the sum of the flow ratios, the optimal Webster cycle length and the effective green time of each phase.

Updated on
Your inputs
veh/h

Value out of range

veh/h

Value out of range

veh/h

Value out of range

veh/h

Value out of range

s

Value out of range

Results

Optimal cycle length (Webster)

61.8 s

Sum of the critical flow ratios Y
0.628
Comfortable: the intersection has spare capacity
Cycle length rounded to 5 s
60 s
Effective green of phase 1
19.8 s
Effective green of phase 2
16.7 s
Effective green of phase 3
13.2 s

Webster’s method gives the cycle length of a traffic signal that gives the lowest average delay. The traffic signal cycle length calculator computes the sum of the flow ratios, the optimal cycle, the cycle rounded to 5 s and the effective green time of each phase of a three-phase intersection.

How the calculation works

  • Enter the critical flow of each of the three phases, the flow of the busiest lane group that moves in that phase, in vehicles per hour.
  • Enter the saturation flow of a lane group (about 1,800 to 1,900 vehicles per hour per lane) and the lost time per phase (start-up and clearance, often 4 s).
  • The calculator computes the flow ratio of each phase, y = q / s, and their sum Y, and then the optimal cycle length of Webster: C = (1.5 L + 5) / (1 − Y), where L is the total lost time.
  • It splits the effective green time between the phases in proportion to their flow ratios.

Example

Three phases have critical flows of 450, 380 and 300 veh/h, a saturation flow of 1,800 veh/h and a lost time of 4 s per phase, so L = 12 s. The flow ratios are 0.250, 0.211 and 0.167, and their sum is Y = 0.628. Webster’s optimal cycle is (1.5 × 12 + 5) / (1 − 0.628) = 61.8 s, or 60 s rounded to 5 s. The effective green, 61.8 − 12 = 49.8 s, is split into 19.8 s, 16.7 s and 13.2 s.

Why it matters

The calculator helps traffic engineering students, planners and city staff to find the order of magnitude of the cycle and of the green splits of a signal, to see how close an intersection is to its capacity, and to compare the effect of a change of demand or of phasing. It gives a first timing before a simulation.

Good to know

Use the critical lane group of each phase, not the sum of all the lanes. Keep the cycle between 60 and 120 s for most urban signals: a very long cycle increases the delay for the pedestrians and the minor movements. If Y is close to 0.85 or more, think about extra lanes, a new phasing or a different intersection design.

The queue wait time calculator estimates the delay in a queue, the stopping distance calculator sets the yellow and the sight distance, the speed distance time calculator converts the speeds and the acceleration calculator covers the start-up of the vehicles.

Frequently asked questions

What is Webster's formula?

Webster's formula gives the cycle length that minimizes the average delay of the vehicles at a signalized intersection: C = (1.5 L + 5) / (1 − Y). L is the total lost time per cycle, the sum of the start-up and clearance losses of all the phases, and Y is the sum of the critical flow ratios. The delay is quite flat around the optimum, so a cycle within 75 to 150% of it gives a delay close to the minimum.

What is a critical flow ratio?

The flow ratio of a phase is the demand flow of its busiest lane group divided by the saturation flow, which is the flow that the lane could discharge in a continuous green. For each phase, only the critical, the highest, flow ratio counts. The sum of these ratios, Y, measures the share of the time that the intersection must use for the green. If Y reaches 1, the intersection is at its capacity.

How is the green time split?

The effective green time, the cycle minus the lost time, is divided between the phases in proportion to their critical flow ratios, so that the degree of saturation is the same on every phase. The actual green is the effective green plus the lost time of the phase minus the yellow and the all-red. Check that each phase also has the minimum green for the pedestrians.

What are the limits of the method?

The method is a simple model with random arrivals and constant flows. It does not account for turning movements, the permitted left turns, the pedestrian phases, the coordination with the neighboring signals or the actuated control. Use it as a starting point, and refer to the Highway Capacity Manual and the local traffic engineer for a real intersection.