Earned value management (EVM) answers three questions about a project in common terms: how much work should be done by now, how much has been done and how much has it cost. By valuing progress in money, it shows whether a project is over budget, behind schedule or both, and projects where it will end if nothing changes.
How the calculation works
- Planned value (PV) = budget × planned progress
- Earned value (EV) = budget × actual progress
- CPI = EV ÷ actual cost, and SPI = EV ÷ PV
- Cost variance = EV − actual cost, and schedule variance = EV − PV
- Estimate at completion (EAC) = budget ÷ CPI
- Estimate to complete = EAC − actual cost, and variance at completion = budget − EAC
- TCPI = (budget − EV) ÷ (budget − actual cost)
Example
A $100,000 project is planned to be 50% done, and is actually 45% done after spending $52,000. PV is $50,000 and EV $45,000. The CPI is 45,000 ÷ 52,000 = 0.87, so each dollar spent has produced 87 cents of work, and the SPI is 0.90. Costs are $7,000 over (the cost variance) and the work is $5,000 behind the plan. If the trend continues, the project will cost $115,556, $15,556 over budget, and the remaining work must be done at a cost efficiency of 1.15 to stay within the budget.
Reading the indices
An index below 1 is a warning, and the farther below, the worse. A project with a CPI below 1 at the 20% mark rarely recovers, so early readings are valuable. A low SPI with a CPI above 1 suggests a resourcing problem; a low CPI with a good SPI suggests that progress is bought at too high a cost.
Using the results
Report EVM regularly, for example every month, and track the trend rather than a single value. Measure progress by finished deliverables, not by effort spent, otherwise earned value will simply follow cost and hide the problem. Revisit the forecast when the scope changes.