Riprap is the layer of rough stone that stops running water from eating away a bank, a slope or a culvert outlet. Ordering it is a matter of area, thickness and weight. This calculator gives the tons to order, the volume in place, the number of truckloads and the cost for an area you want to protect.
How the calculation works
- Volume = length × width × thickness (in feet), converted to cubic yards by dividing by 27
- Tons = volume × weight in place per cubic yard × (1 + waste allowance)
- Truckloads = tons ÷ truck capacity, rounded up
- Cost = tons × price per ton
Riprap in place weighs about 1.4 to 1.6 tons per cubic yard, less than solid rock, because of the gaps between the stones.
Example
A bank 100 ft long and 12 ft wide (measured along the slope) with an 18 in. layer: volume in place is 100 × 12 × 1.5 ÷ 27 = 66.7 yd³. At 1.5 tons per yard and a 10 % allowance, you need 110 tons, delivered in 8 truckloads of 14 tons. At $55 a ton, the material costs $6,050.
Why it matters
Erosion costs far more than the stone to prevent it. A bank that is undercut loses soil, trees and sometimes a building, and the repair is much costlier than an engineered layer of the right size. Ordering an accurate quantity avoids running short in the middle of a job, when trucks are already booked, and avoids leftover stone you must haul away.
Good to know
The size of the stone matters more than the tonnage: it depends on the speed of the water and the slope, and is set by an engineer or the local permitting authority. Use geotextile fabric below the stone. Slopes steeper than 2 horizontal to 1 vertical are hard to stabilize. In many places, working along a stream needs a permit. This tool is for estimating quantities only.
Related tools
The gravel calculator estimates crushed stone by the yard, the retaining wall calculator sizes a block wall, and the stone wall calculator estimates a dry-laid wall.