Labor variance calculator: labor rate variance, efficiency variance and total variance

Enter the actual hours and wage rate and the standard hours and rate to get the labor rate variance, the efficiency variance, the total variance and whether each is favorable.

Updated on
Your inputs
hours

Value out of range

$

Value out of range

hours

Value out of range

$

Value out of range

Results

Total labor variance

$11,300

Unfavorable: the labor cost is above the standard
Labor rate variance
$6,300
Unfavorable: the labor cost is above the standard
Labor efficiency variance
$5,000
Unfavorable: the labor cost is above the standard
Actual labor cost
$111,300
Standard labor cost for the output
$100,000
Total variance as a share of the standard cost
11.30 %

In standard costing, the labor variance compares the real cost of labor with the standard cost for the output. The labor variance calculator splits it into the rate variance and the efficiency variance, adds them into the total labor variance and marks them as favorable or unfavorable.

How the calculation works

  • Enter the actual hours worked and the actual wage rate per hour from the payroll.
  • Enter the standard hours allowed for the output that was really produced, and the standard wage rate from the budget.
  • The calculator gives the rate variance, (actual rate − standard rate) × actual hours, and the efficiency variance, (actual hours − standard hours) × standard rate.
  • It adds them into the total labor variance, compares it with the standard cost, and marks each variance as unfavorable (positive) or favorable (negative).

Example

A plant worked 4,200 hours at $26.50 an hour to make an output whose standard is 4,000 hours at $25.00. The rate variance is (26.50 − 25.00) × 4,200 = $6,300 unfavorable. The efficiency variance is (4,200 − 4,000) × 25 = $5,000 unfavorable. The total is $11,300 unfavorable: the actual cost of $111,300 is above the standard cost of $100,000 by 11.30 %.

Why it matters

The calculator helps accounting students, controllers and plant managers to analyze the difference between budget and reality, to find if a cost overrun comes from the wage rate or from the hours used, and to prepare the variance report for the month. It saves the time of the manual formulas.

Good to know

The calculator uses the usual two-way analysis of the direct labor variance. Positive values are unfavorable and negative values are favorable. The standard hours have to be those allowed for the actual output. Variances are a signal for a question, not a proof of fault: they need an explanation from the production line. It does not cover idle time variances or the variances of overhead.

The material variance calculator applies the same method to materials, the flexible budget variance calculator separates the effect of volume, the overhead rate calculator finds the rate used to apply overhead, and the break-even calculator finds the sales needed to cover costs.

Frequently asked questions

What is the labor rate variance?

The labor rate variance is the difference between the wage rate that was actually paid and the standard rate, multiplied by the actual hours worked. It shows the cost effect of paying more or less per hour than planned, for example because of overtime premiums, a different skill mix, a wage increase or temporary workers. A positive result means the company paid more than the standard, so it is unfavorable.

What is the labor efficiency variance?

The labor efficiency variance is the difference between the actual hours and the standard hours allowed for the real output, multiplied by the standard rate. It shows the cost effect of using more or fewer hours than the standard. Causes are the skill of the workers, the quality of the materials, breakdowns of machines, poor scheduling and training. A positive result means that more hours were used than allowed, so it is unfavorable.

Why are standard hours based on the actual output?

The standard hours must be those allowed for the units that were really produced, not for the budgeted output. If the plant makes 4,000 units and the standard is one hour per unit, the allowed hours are 4,000, even if the budget planned 5,000 units. Using the budgeted output would mix the effect of volume with the effect of efficiency, which is the job of the flexible budget.

Does a favorable variance mean good performance?

Not always. A favorable rate variance can come from hiring less skilled workers, who then use more hours and create an unfavorable efficiency variance. A favorable efficiency variance can come from rushing, which can lower quality and raise the cost of rework. Managers should read the two variances together, and look at the cause before they decide that a result is good or bad.