Overall equipment effectiveness shows how much of the time you plan to produce is really spent making good parts at full speed. This OEE calculator computes availability, performance and quality from your planned time, downtime, ideal cycle time and piece counts, multiplies them into OEE and shows the time lost and the defective pieces.
How the calculation works
- Availability = (planned production time − downtime) ÷ planned production time.
- Performance = ideal cycle time × total pieces ÷ run time.
- Quality = good pieces ÷ total pieces.
- OEE = availability × performance × quality.
- Time lost = (1 − OEE) × planned production time.
Example
A machine is scheduled for 480 minutes and loses 47 minutes to downtime, so availability is 90.2 %. In 433 minutes of running it makes 700 pieces with an ideal cycle of 30 seconds, so performance is 80.8 %. 665 pieces are good, so quality is 95 %. OEE is 69.2 %, which means about 148 minutes of the shift were not fully productive.
Why it matters
A machine can look busy and still waste a third of its capacity on stops, slow running and scrap. OEE splits that loss into three parts you can act on, so a team can see whether the problem is breakdowns, slow cycles or quality, and put its improvement effort where it pays most.
Good to know
Use the ideal cycle time from the design or the best sustained run and not the average, or the performance will look better than it is. Count scrap and rework as non-good pieces, since they use time but do not generate sales. OEE is for a single machine or line, so compare it over time and against a target and not across very different processes. Planned downtime, such as scheduled maintenance, is normally excluded from planned production time. A very high OEE on a bottleneck matters more than on a machine that has spare capacity.