How much work can the team take on in the next sprint?

Enter the team size, the days in the sprint, the hours per day, the focus factor and the days off: get the capacity in focused hours and in story points.

Updated on
Your inputs

Value out of range

Value out of range

Value out of range

%

Value out of range

Value out of range

Value out of range

Results

Capacity of the sprint (focused hours)

313.6

A normal level of availability for the sprint
Available person-days
56.0
Person-days without absences
60
Capacity in story points
62.7
Focused hours per person
52.3

How much can the team take on in the next sprint? Not as much as the number of people times the number of days suggests. Holidays, meetings and interruptions take a share of the time. This calculator computes a sprint’s capacity: the person-days after absences, the focused hours after a focus factor, and an equivalent in story points from the hours per point.

How the calculation works

  • Gross person-days = team members × working days
  • Available person-days = gross person-days − days off
  • Capacity in hours = available person-days × paid hours per day × focus factor
  • Capacity in points = capacity in hours ÷ hours per story point

Example

A team of 6 has a 10-day sprint, with 4 person-days off. The gross total is 60 person-days and 56 are available. With 8 paid hours a day and a focus factor of 70%, the capacity is 313.6 focused hours, or 52.3 hours per person. At 5 hours per point, it is 62.7 points.

Why it matters

Overloading a sprint is one of the most common causes of missed commitments. A capacity calculation, repeated every sprint, makes absences visible and sets a realistic target. Comparing capacity with past velocity also helps calibrate the focus factor.

Good to know

The focus factor and hours per point are estimates and differ between teams. People do not have identical skills, and some tasks need a specific person, so the total hides bottlenecks. Use the capacity to check a plan, not as a quota, and revisit it after a few sprints. Remember that public holidays, training days, on-call duty and planned support work all reduce capacity, and that a newly formed team or a new tool often lowers the focus factor for the first sprints. A short note of who is away in each sprint keeps the plan honest. This tool is for education.

The sprint velocity calculator forecasts the number of sprints in a backlog, the burndown forecast calculator tracks progress in a sprint, and the meeting cost calculator shows the cost of time spent in meetings.

Frequently asked questions

What is team capacity?

The amount of work a team can take on in a sprint: the people available, multiplied by the days, hours and share of time they can devote to planned work. It is the input to sprint planning.

What is a focus factor?

The share of working time spent on sprint work, after meetings, support, email and other interruptions. Teams typically find 60 to 80 percent, and new teams or those with many interruptions find less.

How do I convert hours to story points?

Divide the hours by the number of hours the team usually needs for a point. Calibrate it using past sprints: hours worked divided by points completed. Many teams prefer to plan in velocity and use hours only as a cross-check.

Should the capacity match the velocity?

They should be close. If the capacity in points is far above the velocity, the focus factor or the hours per point are probably too optimistic, and the sprint will be overloaded.