How much can the team take on in the next sprint? Not as much as the number of people times the number of days suggests. Holidays, meetings and interruptions take a share of the time. This calculator computes a sprint’s capacity: the person-days after absences, the focused hours after a focus factor, and an equivalent in story points from the hours per point.
How the calculation works
- Gross person-days = team members × working days
- Available person-days = gross person-days − days off
- Capacity in hours = available person-days × paid hours per day × focus factor
- Capacity in points = capacity in hours ÷ hours per story point
Example
A team of 6 has a 10-day sprint, with 4 person-days off. The gross total is 60 person-days and 56 are available. With 8 paid hours a day and a focus factor of 70%, the capacity is 313.6 focused hours, or 52.3 hours per person. At 5 hours per point, it is 62.7 points.
Why it matters
Overloading a sprint is one of the most common causes of missed commitments. A capacity calculation, repeated every sprint, makes absences visible and sets a realistic target. Comparing capacity with past velocity also helps calibrate the focus factor.
Good to know
The focus factor and hours per point are estimates and differ between teams. People do not have identical skills, and some tasks need a specific person, so the total hides bottlenecks. Use the capacity to check a plan, not as a quota, and revisit it after a few sprints. Remember that public holidays, training days, on-call duty and planned support work all reduce capacity, and that a newly formed team or a new tool often lowers the focus factor for the first sprints. A short note of who is away in each sprint keeps the plan honest. This tool is for education.