Concrete evaporation rate calculator: risk of plastic shrinkage cracking in hot weather

Enter the concrete and air temperatures, the relative humidity, the wind speed and the exposed area to get the evaporation rate, the water lost per hour and the ratio to the ACI 305 limit of 0.2 lb/ft²/h.

Updated on
Your inputs
°F

Value out of range

°F

Value out of range

%

Value out of range

mph

Value out of range

ft²

Value out of range

Results

Ratio to the limit of 0.2 lb/ft²/h

0.90

Evaporation rate
0.179 lb/ft²/h
Between 0.1 and 0.2 lb/ft²/h: take precautions, such as fog misting and windbreaks
Water lost from the exposed surface
179 lb/h

The concrete evaporation rate calculator gives the evaporation rate of the surface of fresh concrete with the ACI 305 equation, the water lost per hour and the ratio to the limit of 0.2 lb/ft²/h, to assess the risk of plastic shrinkage cracking in hot, dry or windy weather.

How the calculation works

  • Enter the concrete temperature, the air temperature, the relative humidity and the wind speed.
  • Enter the exposed area of the pour, to find the quantity of water that the surface loses.
  • The calculator finds the evaporation rate with the equation of Menzel and Uchida (ACI 305), the water lost per hour and the ratio to the limit of 0.2 lb/ft²/h.

Example

A slab is placed at a concrete temperature of 85 °F, in air at 90 °F, with a relative humidity of 40 % and a wind of 10 mph. The evaporation rate is (85^2.5 − 0.40 × 90^2.5) × (1 + 0.4 × 10) × 10⁻⁶ = 0.179 lb/ft²/h. On 1,000 ft² of exposed surface, the loss is 179 lb/h of water. The rate is 0.90 times the limit of 0.2 lb/ft²/h, so protection is needed.

Why it matters

The calculator helps concrete contractors, finishers, inspectors and engineers to decide if a pour is at risk in hot or windy weather, to compare the effect of the temperatures, the wind and the humidity and to plan the protection of the slab.

Good to know

Measure the temperatures, the humidity and the wind at the site just before and during the pour. Prepare the windbreaks, the misting and the curing materials in advance, and keep the concrete temperature low. Start the curing as soon as the finishing allows it. Record the readings and the measures taken in the daily log, so that the decision to place or to postpone is documented.

The concrete curing calculator plans the curing, the concrete volume calculator gives the volume, the concrete crack width calculator checks the cracks and the pool evaporation calculator shows the water loss of a water surface.

Frequently asked questions

Why does the evaporation rate matter for fresh concrete?

When the water evaporates from the surface of fresh concrete faster than the bleed water can rise, the surface dries out and shrinks while the concrete below is still plastic. This causes plastic shrinkage cracks, which are short and wide, appear in the first hours and can go deep. Hot weather, wind, low humidity and a high concrete temperature increase the evaporation.

What equation is used?

The calculator uses the equation behind the nomograph of ACI 305: E = (Tc^2.5 − r Ta^2.5) (1 + 0.4 V) × 10⁻⁶ in lb/ft²/h, with the concrete temperature Tc and the air temperature Ta in °F, the relative humidity r as a fraction and the wind speed V in mph. In SI units, E = 5 [(Tc + 18)^2.5 − r (Ta + 18)^2.5] (V + 4) × 10⁻⁶ in kg/m²/h, with the temperatures in °C and the wind in km/h.

What limit should be respected?

A rate of 0.2 lb/ft²/h (1.0 kg/m²/h) is the usual limit at which precautions must be taken against the plastic shrinkage cracking. For concretes with silica fume or other mixes that bleed little, the limit may be lower, such as 0.1 lb/ft²/h (0.5 kg/m²/h). The precautions are windbreaks, sunshades, fog misting, evaporation retarders, cooled materials, a quick start of the curing and a placement at night.

What are the limits of the calculator?

The calculator gives an estimate from the four weather and concrete parameters. It does not include the solar radiation, the temperature of the surface of the formwork or the subgrade, the bleeding rate of the particular mix, the absorption of the subgrade or the effect of the slump. The real risk should be watched on site, and the concrete finished and cured according to the specification.

Was this calculator helpful?

Thanks for your feedback!

Results are estimates provided for information purposes. They do not replace professional advice.