Results

Vibrators to bring to the site

4

Radius of action
12 in
Maximum spacing of the insertions
18 in
Capacity of one vibrator
21.0 yd³/h
Vibrators needed (theoretical)
2.86

The concrete vibrator calculator gives the radius of action, the maximum spacing of the insertions, the capacity of one vibrator and the number of vibrators needed for a concrete placement, from the diameter of the head, the lift thickness, the time per insertion and the placement rate.

How the calculation works

  • Enter the diameter of the vibrator head and the thickness of the lift of concrete.
  • Enter the time per insertion, the efficiency of the operator, the placement rate and the number of spare vibrators.
  • The calculator finds the radius of action, the spacing of the insertions, the capacity of one vibrator and the number of vibrators to bring.

Example

A vibrator with a head of 2 in has a radius of action of about 6 × 2 = 12 in, so the insertions are spaced at most 1.5 × 12 = 18 in. With a lift of 18 in, each insertion consolidates 18 × 18 × 18 / 46,656 = 0.125 yd³. With 15 s per insertion and an efficiency of 0.7, there are 3,600 / 15 × 0.7 = 168 insertions per hour, so the capacity is 21.0 yd³/h. For a rate of 60 yd³/h, the number of vibrators is 2.86, so 4 are brought with 1 spare.

Why it matters

The calculator helps concrete foremen, site engineers, inspectors and students to plan the consolidation of walls, columns and slabs, to choose the size of the vibrators, and to be sure that enough vibrators are on the site for the planned rate of the pour.

Good to know

Use the largest vibrator that fits between the bars of the reinforcement, and keep a spare vibrator, an extra head and a power source on the site for the whole pour. Do not use the vibrator to move the concrete sideways, because it causes segregation, and do not touch the forms or the bars with the head. Consolidate each lift quickly after the placement, and stop when the surface has a uniform shine and the large bubbles no longer rise.

The concrete volume calculator gives the quantity to place, the concrete formwork calculator checks the pressure on the forms, the concrete curing calculator plans the curing after the pour and the labor productivity calculator gives the work output of the crew.

Frequently asked questions

What is the radius of action of a vibrator?

The radius of action is the distance from the vibrator head over which the concrete is visibly consolidated. It depends on the diameter and the frequency of the head and on the slump of the mix. A rule of thumb is about 6 times the diameter of the head, so a 2 in head reaches 12 in, which is in line with the guide ACI 309 for heads of 1.25 to 2.5 in, with a radius of 7 to 14 in.

How far apart should the insertions be?

The insertions are spaced so that the circles of action overlap, with a distance not larger than 1.5 times the radius of action. The head is inserted vertically, quickly, and is withdrawn slowly at about 3 in per second, with the head going into the lift below by about 6 in. Each insertion lasts 5 to 15 seconds, until the air bubbles stop and the surface is shiny.

What is a good thickness of lift?

The lift of fresh concrete should not be thicker than the length of the vibrator head, which is about 18 in for a common head, so that the vibrator can reach the bottom of the lift and the layer below. A thicker lift traps air and gives a poor surface on the forms. The next lift must be placed before the previous one is set, so that the vibrator joins the two layers.

What are the limits of the calculator?

The calculator gives an estimate for a simple grid of insertions and for a normal-weight mix with a slump of 3 to 6 in. It does not include the congestion of the reinforcement, the slump that is very low or very high, the form vibrators, the vibrating screeds for slabs or the self-consolidating concrete, which does not need vibration. The crew must watch the concrete and adjust the work to the real result.