Excavator productivity calculator: hourly production of a hydraulic excavator

Enter the bucket size, the fill factor, the cycle time, the efficiency, the swell and the truck capacity to get the cycles per hour, the loose and bank production and the time to load a truck.

Updated on
Your inputs
yd³

Value out of range

Value out of range

s

Value out of range

Value out of range

%

Value out of range

yd³

Value out of range

Results

Production, bank volume

196 yd³/h

Cycles per hour
163.6
Production, loose volume
244 yd³/h
Time to load one truck
2.9 min

The excavator productivity calculator gives the cycles per hour, the production in loose and bank volume and the time to load one truck of a hydraulic excavator, from the bucket size, the fill factor, the cycle time, the efficiency and the swell.

How the calculation works

  • Enter the bucket capacity, the fill factor of the bucket and the cycle time of the excavator.
  • Enter the job efficiency, which is the working share of the hour, the swell of the material and the capacity of the trucks.
  • The calculator finds the cycles per hour, the production in loose and in bank volume and the time to load one truck.

Example

An excavator with a bucket of 2 yd³ has a fill factor of 0.9, a cycle time of 22 s and an efficiency of 0.83 (50 min/h). The cycles per hour are 3600 / 22 = 163.6. The loose production is 2 × 0.9 × 163.6 × 0.83 = 244 yd³/h. With a swell of 25 %, the bank production is 244.5 / 1.25 = 196 yd³/h. A truck of 12 yd³ is loaded in 12 / 244.5 × 60 = 2.9 min.

Why it matters

The calculator helps estimators, site managers, earthwork contractors and students to estimate the time and the cost of an excavation, to match the excavator and the trucks and to compare machines of different size.

Good to know

Use the cycle time of the real conditions, such as the depth of the cut and the swing angle, and the efficiency of your own job records. Plan the number of trucks so that the excavator never waits, and add the moves and the maintenance to the schedule. Remember that the bank volume, not the loose volume, is what the earthwork quantities and the payment items usually refer to.

The earthwork swell and shrink calculator converts the bank, loose and compacted volumes, the excavation calculator gives the volume to dig, the labor productivity calculator gives the output per hour and the dumpster size calculator estimates the container for waste.

Frequently asked questions

How is the production of an excavator calculated?

The production is the number of cycles per hour times the volume moved in each cycle, corrected by the job efficiency. The volume per cycle is the bucket capacity times the fill factor. The cycle time includes the digging, the swing to the truck, the dump and the return, and depends on the size of the machine, the soil, the depth of the cut and the swing angle. For a medium excavator, a cycle of 15 to 25 seconds is common.

What are the fill factor and the efficiency?

The fill factor is the ratio of the real load of the bucket to its rated capacity. It is 0.8 to 1.1 for the moist loam and the sand, 0.6 to 0.9 for hard clay and blasted rock. The job efficiency is the share of the hour that the machine really works, often 0.83 (50 minutes) for a good operation, and less for a poor management, a difficult site or a night work.

Why are the loose and bank volumes different?

When the soil is dug, it swells because the voids increase. A cubic yard of soil in place, the bank volume, becomes 1.1 to 1.5 loose cubic yards. The bucket and the trucks are filled with loose soil, but the quantities of a project and the payment are usually in bank cubic yards, so the production is given in both. The swell factor depends on the soil, for example 25 % for common earth and 40 % for rock.

What are the limits of the calculator?

The calculator uses the cycle time that you enter, and gives an estimate for a steady operation. It does not include the haul distance and the number of trucks needed for a balanced fleet, the moves of the machine, the waiting time of the trucks, the weather, the break of the digging in the hard soils or the cost per cubic yard. For a real project, the production should be checked with field data.

Was this calculator helpful?

Thanks for your feedback!

Results are estimates provided for information purposes. They do not replace professional advice.