Earthwork swell and shrink calculator: how much soil to haul and to import

Enter the bank volume of an excavation, the swell factor, the shrinkage on compaction, the truck capacity and the compacted fill needed to get the loose volume, the truckloads and the surplus or shortage of soil.

Updated on
Your inputs
yd³

Value out of range

%

Value out of range

%

Value out of range

yd³

Value out of range

yd³

Value out of range

Results

Truckloads (rounded up)

90

Loose volume to haul
1,250 yd³
Compacted volume of the excavated soil
900 yd³
Bank volume needed for the fill
1,222.2 yd³
Surplus (+) or shortage (−) of compacted soil
-200 yd³
Shortage: import soil to complete the fill

Soil changes volume when it is dug up and when it is compacted. The earthwork swell and shrink calculator converts a bank volume into a loose volume and a compacted volume, counts the truckloads and shows the surplus or shortage of soil for a fill.

How the calculation works

  • Enter the volume excavated in the ground, called the bank volume, in cubic yards.
  • Enter the swell factor, the increase of volume when the soil is dug up: about 10% to 15% for sand, 20% to 30% for clay and loam, and 40% or more for rock. Enter the shrinkage of the soil when it is compacted in the fill.
  • Enter the capacity of a truck as a loose volume and the compacted volume that the fill needs.
  • The calculator gives the loose volume to haul, the compacted volume, the number of truckloads, the bank volume needed for the fill and the surplus or shortage.

Example

A job excavates 1,000 yd³ (bank) of a clay loam with a 25% swell and a 10% shrinkage when compacted. The loose volume to haul is 1,000 × 1.25 = 1,250 yd³, which is 90 truckloads of 14 yd³ (89.3, rounded up). The excavated soil makes 1,000 × 0.90 = 900 yd³ once compacted. The fill needs 1,100 yd³ compacted, so it takes 1,100 / 0.90 = 1,222.2 yd³ of bank soil, and the site has a shortage of 200 yd³ to import.

Why it matters

The calculator helps contractors, estimators, landscapers and civil engineering students to plan the hauling of an excavation, to price the trucking and the disposal, and to see if a site balances between cut and fill. A wrong assumption about swell can double the number of trucks that the schedule needs.

Good to know

Always state the basis of a volume: bank, loose or compacted. Take the swell and the shrinkage from the geotechnical report, or from a test fill. Round the truckloads up, and include the volume of the topsoil, which is stripped and stored apart. Remember that a wet clay swells more than a dry sand.

The excavation calculator gives the bank volume of a hole, the soil compaction calculator controls the density of the fill, the gravel calculator estimates the import of stone and the retaining wall calculator covers the backfill behind a wall.

Frequently asked questions

What are bank, loose and compacted volumes?

The same soil has three volumes. The bank volume is the soil in place in the ground, before it is dug. The loose volume is the soil after it is excavated, when it is bulked up by air in the voids, and it is the volume that a truck carries. The compacted volume is the soil after it is placed and compacted in a fill, usually a little smaller than the bank volume.

What is the swell factor?

The swell factor is the percentage by which the volume increases when the soil is dug: loose volume = bank volume × (1 + swell). Typical values are 10% to 15% for sand and gravel, 20% to 30% for clay and loam, and 40% to 60% for blasted rock. The factor sets the number of truckloads and the size of the stockpile.

What is the shrinkage?

When the soil is placed in layers and compacted, it ends denser than in its natural state. The compacted volume is the bank volume × (1 − shrinkage). Shrinkage is often 5% to 15% for clay and loam, and close to zero for clean sand. The same soil needs more bank volume than the fill volume, which is why a site that balances on paper can be short in practice.

How should the result be used?

Use the truckloads for the haul schedule and the cost of trucking. Use the surplus or shortage to plan the import or the export of soil. The values are estimates: measure the swell and the shrinkage on the soil of the site with a field density test, and add a margin of 5% to 10% for waste, trench over-excavation and rounding of the loads.