Overtime productivity loss and crew cost calculator

Enter the crew size, the wage, the regular and worked hours, the overtime multiplier and the efficiency lost per overtime hour to get the true cost of the extra hours.

Updated on
Your inputs
workers

Value out of range

$/h

Value out of range

h

Value out of range

h

Value out of range

Value out of range

%

Value out of range

Results

Cost per productive hour

71.37 $/h

Average efficiency of the week
85.0 %
Productive hours per worker per week
51.0 h
Increase over the straight-time cost
37.3 %
A very high premium: overtime is an expensive way to speed up the work
Weekly payroll of the crew
43,680 $
Productive crew hours per week
612 h

The overtime productivity loss calculator gives the average efficiency of a long week, the productive hours, the cost per productive hour, the increase over straight time and the weekly payroll of a crew.

How the calculation works

  • Enter the crew size, the loaded wage rate and the regular hours per week.
  • Enter the hours worked per week, the overtime pay multiplier and the efficiency lost per overtime hour.
  • The calculator gives the average efficiency, the productive hours, the cost per productive hour and the payroll of the crew.

Example

A crew of 12 workers at $52 per hour works 60 hours a week instead of 40. The 20 overtime hours cost 1.5 times the rate, so a worker is paid the equivalent of 70 straight-time hours. With 0.75 % of efficiency lost per overtime hour, the average efficiency is 85.0 % and a worker produces 51.0 productive hours. One productive hour costs $71.37, which is 37.3 % more than straight time. The weekly payroll of the crew is $43,680 for 612 productive crew hours.

Why it matters

The calculator helps project managers, schedulers, estimators and owners to see the real cost of speeding up work with overtime, to explain it in a claim or a change order, and to compare overtime with a second shift or a bigger crew.

Good to know

Use overtime for short peaks, not for months, since the loss grows with the length of the period. Compare the cost per productive hour with the cost of adding workers or a second shift, which keeps the efficiency of the regular hours. Record the actual hours and output so that you have your own loss rate, and take account of the safety and quality risk of tired workers.

The labor productivity calculator measures the output per hour, the overtime pay calculator gives the pay of the extra hours, the man-hours calculator converts a quantity into labor hours and the learning curve calculator models the improvement of repeated work.

Frequently asked questions

Why does overtime lose efficiency?

Long weeks cause fatigue, more errors and rework, more accidents, lower morale and a lower output per hour. Studies of construction trades find that the output per hour falls as the week gets longer and as the number of weeks of overtime grows. In a 60-hour week the average efficiency can be 10 to 20 % below that of a 40-hour week. The effect is larger for physical work and for long periods.

How does the calculator model it?

The efficiency of the week is 1 minus the loss per overtime hour times the number of overtime hours, with a floor of 30 %. The productive hours are the hours worked times that efficiency. The pay is the regular hours plus the overtime hours times the multiplier. The cost per productive hour is the pay divided by the productive hours, which is the figure to compare with the straight-time rate.

What loss rate should I use?

The published tables of the trade associations and the studies give a loss of about 0.5 to 1 % per overtime hour per week for a few weeks, and more for a long period. Use your own records of the hours and the output when you have them. The value of 0.75 % is a middle figure, and it is a good idea to test the result with 0.5 % and 1 % to see how sensitive the cost is.

What does the calculator leave out?

The calculator leaves out the cost of the lighting, the supervision, the safety risk, the quality problems and the effect on the following weeks. It also assumes the same loss for each overtime hour, and a fixed multiplier. Real contracts often have different overtime rules, shift premiums and daily limits. Compare the result with the cost of a second shift or of more workers before you decide.