The overtime productivity loss calculator gives the average efficiency of a long week, the productive hours, the cost per productive hour, the increase over straight time and the weekly payroll of a crew.
How the calculation works
- Enter the crew size, the loaded wage rate and the regular hours per week.
- Enter the hours worked per week, the overtime pay multiplier and the efficiency lost per overtime hour.
- The calculator gives the average efficiency, the productive hours, the cost per productive hour and the payroll of the crew.
Example
A crew of 12 workers at $52 per hour works 60 hours a week instead of 40. The 20 overtime hours cost 1.5 times the rate, so a worker is paid the equivalent of 70 straight-time hours. With 0.75 % of efficiency lost per overtime hour, the average efficiency is 85.0 % and a worker produces 51.0 productive hours. One productive hour costs $71.37, which is 37.3 % more than straight time. The weekly payroll of the crew is $43,680 for 612 productive crew hours.
Why it matters
The calculator helps project managers, schedulers, estimators and owners to see the real cost of speeding up work with overtime, to explain it in a claim or a change order, and to compare overtime with a second shift or a bigger crew.
Good to know
Use overtime for short peaks, not for months, since the loss grows with the length of the period. Compare the cost per productive hour with the cost of adding workers or a second shift, which keeps the efficiency of the regular hours. Record the actual hours and output so that you have your own loss rate, and take account of the safety and quality risk of tired workers.