Learning curve calculator: how fast does production time fall with experience?

Enter the first unit time, the learning rate and a unit number to get the time for that unit, the total time and the labor cost.

Updated on
Your inputs
hours

Value out of range

%

Value out of range

Value out of range

$

Value out of range

Results

Time for unit n

28.4 hours

Total labor cost

$73,251

Total time for all n units
2,093 hours
Average time per unit
41.9 hours
Reduction versus the first unit
71.6%
Learning exponent
-0.322

Workers and processes get faster with repetition, and Wright’s law describes how the time for each unit falls as total output grows. This learning curve calculator uses the first unit time and the learning rate to give the time for any unit, the total and average time for the first n units and the labor cost.

How the calculation works

  • Learning exponent b = ln(learning rate) ÷ ln(2), a negative number for rates below 100 %.
  • Time for unit n = time for the first unit × n^b.
  • Total time ≈ time for the first unit × n^(b + 1) ÷ (b + 1), the integral of the curve.
  • Average time = total time ÷ n.
  • Labor cost = total time × labor cost per hour.

Example

A first unit takes 100 hours and the process has an 80 % learning rate, so each doubling of output cuts the unit time by 20 %. The exponent is −0.322, and unit 50 takes about 28.4 hours, a 72 % reduction. All 50 units take about 2,090 hours, or 41.9 hours on average, and cost about $73,200 at $35 an hour.

Why it matters

Bids and budgets that ignore the learning curve overestimate the labor for long runs, while those that assume the curve continues forever underestimate it. The model gives a defensible way to price a contract, plan hiring for a ramp-up, or compare the cost of a first batch with a later batch from the same process.

Good to know

The learning rate is estimated from your own history: divide the time of a later unit by the time of a unit with half the cumulative output. The cumulative average version used by some industries gives slightly different totals, so be consistent in how you measure it. Learning slows when workers change, tools change or the product design changes, because the curve restarts for the new elements. Include setup, rework and idle time only if they are part of the data that you used to estimate the rate.

The labor productivity calculator measures output per hour, the PERT estimate calculator handles uncertain task durations, and the team capacity calculator plans sprint hours.

Frequently asked questions

What is a learning curve?

The observation that the time or cost to make a unit falls by a constant percentage each time cumulative output doubles.

What is an 80 percent learning rate?

Each time the number of units doubles, the time for a unit drops to 80 percent of what it was.

What learning rates are typical?

Complex assembly such as aircraft often shows 75 to 85 percent, and simple repetitive work shows 90 to 95 percent.

Does the curve go on forever?

No. Real processes level off once the work is routine, so extrapolate beyond a few hundred units with care.

Was this calculator helpful?

Thanks for your feedback!

Results are estimates provided for information purposes. They do not replace professional advice.