Ready-mix truck fleet calculator: how many concrete trucks a pour needs

Enter the placement rate, the truck capacity, the loading, travel and unloading times and the reserve to get the cycle, the deliveries per hour, the interval and the number of trucks.

Updated on
Your inputs
yd³/h

Value out of range

yd³

Value out of range

min

Value out of range

min

Value out of range

min

Value out of range

Value out of range

Results

Trucks to dispatch with the reserve

9

Round trip cycle of a truck
75 min
Deliveries needed per hour
6.00 loads/h
Interval between two trucks
10.0 min
Trucks needed (theoretical)
7.50

The ready-mix truck fleet calculator gives the round trip cycle, the deliveries per hour, the interval between trucks and the number of trucks needed for a concrete pour, from the placement rate, the capacity of the trucks and the loading, travel and unloading times.

How the calculation works

  • Enter the placement rate required at the site and the capacity of a truck load.
  • Enter the loading time at the plant, the one-way travel time, the unloading and washout time at the site and the number of reserve trucks.
  • The calculator finds the round trip cycle, the deliveries per hour, the interval between trucks, the theoretical number of trucks and the number to dispatch.

Example

A pour needs 60 yd³/h and the trucks carry 10 yd³, so 6.00 loads per hour are needed, one every 10.0 min. A truck takes 10 min to load, 25 min to drive each way and 15 min at the site, so the cycle is 10 + 2 × 25 + 15 = 75 min. The theoretical number of trucks is 6 × 75 / 60 = 7.50, which is rounded up to 8. With 1 reserve truck, 9 trucks are dispatched.

Why it matters

The calculator helps site managers, concrete suppliers, dispatchers, estimators and students to plan the supply of a big pour, to avoid the cold joints and the long waits at the site, and to compare the effect of a longer haul or a slower placement on the fleet.

Good to know

Use times measured on the same route at the same hour, and plan the first trucks to arrive before the crew is ready. Keep the pump and the placing crew sized for the delivery rate, because a pour is only as fast as its slowest step. Warn the plant of the start time, the rate and the slump, and keep a reserve truck for the long pours and the hot days.

The concrete volume calculator gives the quantity to order, the labor productivity calculator gives the work output of the crew, the dumpster size calculator compares the loads of a container and the earthwork swell and shrink calculator converts the haul volumes.

Frequently asked questions

How is the number of concrete trucks calculated?

The number of trucks is the number of deliveries per hour times the duration of the round trip of a truck, in hours. The deliveries per hour are the placement rate divided by the load of a truck. The round trip includes the loading at the plant, the travel to the site, the unloading and the waiting, the washout and the return to the plant.

Why is a reserve truck added?

A truck can break down, be caught in the traffic or be delayed at the plant. A cold joint in a slab or a wall is expensive and can reduce the strength of the element, so the supply must not stop. One reserve truck, or more for a long and critical pour, is cheap compared with the cost of an interruption.

What is a good interval between two trucks?

The interval must be close to the time that the crew needs to place a load, so that the truck at the site finishes just when the next one arrives. If the interval is longer than the placing time, the crew waits and the risk of a cold joint grows. If the interval is much shorter, the trucks queue at the site and the concrete ages in the drum, and the standards limit the time between the batching and the discharge to about 90 minutes.

What are the limits of the calculator?

The calculator uses constant times and does not include the variations of the traffic, the breakdowns, the changes of the placement rate, the hot weather that shortens the time of discharge, the batching capacity of the plant or the number of pumps at the site. For a large pour, plan the dispatch with the plant and update the rate with real times.