The slab shoring spacing calculator gives the load on each shore that supports the formwork of an elevated concrete slab, from the thickness, the formwork, the construction live load and the spacing, with the capacity ratio and the largest spacing of the shores.
How the calculation works
- Enter the thickness of the concrete slab, the dead load of the formwork and the construction live load, which is at least 50 psf in ACI 347.
- Enter the spacing of the shores in both directions and the allowable load of one shore from the manufacturer.
- The calculator finds the dead load of the fresh slab, the total design load, the load on a shore, the ratio of the capacity to the load and the largest square spacing that the shores can carry.
Example
An 8 in slab of normal-weight concrete weighs 150 × 8 / 12 = 100.0 psf. With 5 psf of formwork and 50 psf of construction live load the design load is 155.0 psf. Shores at 4 ft by 4 ft each carry 155 × 16 = 2,480 lb. With an allowable load of 4,000 lb, the capacity is 1.61 times the load, and the largest square spacing is √(4,000 / 155) = 5.08 ft.
Why it matters
The calculator helps concrete contractors, formwork designers, site engineers and students to check the number and the spacing of the shores under a slab, to see the effect of the thickness of the slab and of the live load and to avoid an overload that could lead to a collapse. It gives a quick check before the shoring drawing.
Good to know
Use the allowable load of the shore at the height of use, since it decreases when the shore is extended. Add the loads of the concrete placing, such as the buggies and the pile of concrete, and increase the live load at the edges. Check the floors that carry the shores, and keep the shores plumb and well braced.
Related tools
The concrete formwork calculator gives the area of the forms, the concrete volume calculator gives the quantity of the pour, the load combinations calculator combines design loads and the wood beam span calculator checks the joists and stringers.