Not every task in a project is equally urgent, and the difference is the slack. This slack time calculator takes the earliest start, the duration, the latest finish and the earliest start of the next activity to give the earliest finish, the latest start, the total slack and the free float.
How the calculation works
- Earliest finish EF = earliest start + duration. It is when the activity ends if it starts as early as possible.
- Latest start LS = latest finish − duration. It is the last day the activity can start without delaying the project.
- Total slack (float) = latest finish − earliest finish = LS − ES. An activity with zero slack is on the critical path.
- Free float = earliest start of the next activity − earliest finish. It is the delay that does not affect any following activity.
Example
An activity can start on day 5, lasts 8 days, must be done by day 18, and the next activity can start on day 14. The earliest finish is 5 + 8 = day 13 and the latest start is 18 − 8 = day 10. The total slack is 18 − 13 = 5 days, which is 62.5% of the duration. The free float is 14 − 13 = 1 day.
Why it matters
Project managers, students of project management and site supervisors use slack to find the critical path, to decide which tasks can wait and to see how much delay a project can take. It is a core idea of the critical path method.
Good to know
The calculator looks at one activity at a time and uses numbers of days that you provide. In a real project the earliest and latest dates come from a full network of dependencies, calendars and resources, which scheduling software computes. Slack is shared between activities on a path, so using it all on one task leaves none for the others. Treat the result as a guide for discussion.
Related tools
The PERT estimate calculator gives an expected duration, the business days calculator counts working days between dates and the sprint velocity calculator plans work in agile teams.