Slack time calculator: how long can a task slip before the project is late?

Enter the earliest start, the duration, the latest finish and the next start to get the earliest finish, the latest start, the total slack and the free float.

Updated on
Your inputs
day

Value out of range

days

Value out of range

day

Value out of range

day

Value out of range

Results

Total slack (float)

5 days

Room to slip
Earliest finish (EF)
13 days
Latest start (LS)
10 days
Free float
1 days
Slack as a share of the duration
62.5%

Not every task in a project is equally urgent, and the difference is the slack. This slack time calculator takes the earliest start, the duration, the latest finish and the earliest start of the next activity to give the earliest finish, the latest start, the total slack and the free float.

How the calculation works

  • Earliest finish EF = earliest start + duration. It is when the activity ends if it starts as early as possible.
  • Latest start LS = latest finish − duration. It is the last day the activity can start without delaying the project.
  • Total slack (float) = latest finish − earliest finish = LS − ES. An activity with zero slack is on the critical path.
  • Free float = earliest start of the next activity − earliest finish. It is the delay that does not affect any following activity.

Example

An activity can start on day 5, lasts 8 days, must be done by day 18, and the next activity can start on day 14. The earliest finish is 5 + 8 = day 13 and the latest start is 18 − 8 = day 10. The total slack is 18 − 13 = 5 days, which is 62.5% of the duration. The free float is 14 − 13 = 1 day.

Why it matters

Project managers, students of project management and site supervisors use slack to find the critical path, to decide which tasks can wait and to see how much delay a project can take. It is a core idea of the critical path method.

Good to know

The calculator looks at one activity at a time and uses numbers of days that you provide. In a real project the earliest and latest dates come from a full network of dependencies, calendars and resources, which scheduling software computes. Slack is shared between activities on a path, so using it all on one task leaves none for the others. Treat the result as a guide for discussion.

The PERT estimate calculator gives an expected duration, the business days calculator counts working days between dates and the sprint velocity calculator plans work in agile teams.

Frequently asked questions

What is slack time?

Slack, or float, is the time that an activity can be delayed without delaying the end of the project. It is the gap between the earliest and the latest dates at which the activity can finish. Activities with no slack form the critical path, and any delay on them delays the whole project.

What is the difference between total slack and free float?

Total slack is the delay that the project can accept without missing its end date, and it is shared with the activities after it. Free float is the delay that does not push back the start of the very next activity. Free float is never larger than the total slack.

What if the slack is negative?

A negative slack means that the earliest finish is later than the latest finish allowed, so the schedule cannot be met as it stands. The calculator accepts only valid inputs for simplicity, but in a plan this means you must shorten the task, add resources or move the deadline.

How should I use slack in planning?

Use slack to decide where to put resources and risk. Tasks with little slack need close follow-up, and tasks with a lot of slack can be moved to level the workload. Keep in mind that using the slack on one task takes it away from the others on the same path.