How long will a task really take, and what is the chance of meeting the deadline?

Enter the optimistic, most likely and pessimistic durations and a deadline: get the PERT expected duration, the standard deviation, a 95% range and the probability of finishing on time.

Updated on
Your inputs

Value out of range

Value out of range

Value out of range

Value out of range

Results

Expected duration (PERT)

16.67 days

A fair chance of meeting the deadline, but with limited margin
Standard deviation
3.33 days
95% range: lower bound
10.0 days
95% range: upper bound
23.3 days
Probability of finishing by the deadline
84.1%

Estimating a task with one number hides the uncertainty. The PERT method asks for three: an optimistic, a most likely and a pessimistic duration. It combines them into an expected duration and a standard deviation, then gives the probability of meeting a deadline. This calculator does the arithmetic for a single task, or for a whole path if you enter its totals.

How the calculation works

  • Expected duration = (optimistic + 4 × most likely + pessimistic) ÷ 6
  • Standard deviation = (pessimistic − optimistic) ÷ 6
  • 95% range = expected ± 2 × standard deviation
  • Probability of meeting the deadline = normal distribution at (deadline − expected) ÷ standard deviation

Example

The optimistic estimate is 10 days, the most likely 15 and the pessimistic 30. The expected duration is 16.7 days with a standard deviation of 3.3 days. A 95% range runs from 10.0 to 23.3 days. With a 20-day deadline, the probability of finishing in time is 84.1%.

Why it matters

A deadline with a probability attached is a better basis for decisions than a single date. PERT makes teams think about what could go wrong, and shows how much a long pessimistic tail adds to the expected duration. For a chain of independent tasks, the expected durations add up, as do the variances.

Good to know

The method treats the beta distribution as roughly normal, which is only an approximation, and assumes independent tasks. Estimates are often over-optimistic, so ask for the pessimistic case first and compare the result with past projects. A single critical path hides parallel paths that can also run late, and in a real project the delays of tasks are often correlated, which makes the total less predictable than the independent model suggests. For a project with many tasks, apply the method to each and then add the expected durations along the critical path. This tool is for education.

The earned value calculator tracks cost and schedule performance, the sprint velocity calculator forecasts a backlog, and the normal distribution calculators give probabilities for other thresholds.

Frequently asked questions

What is the PERT estimate?

A weighted average of three estimates: optimistic (O), most likely (M) and pessimistic (P). The expected duration is (O + 4M + P) ÷ 6, and the standard deviation is (P − O) ÷ 6.

Where does the probability of meeting the deadline come from?

From a normal approximation: the probability is the cumulative normal distribution at (deadline − expected) ÷ standard deviation. A deadline equal to the expected duration gives 50 percent.

Why is the expected duration above the most likely value?

Because the pessimistic estimate is usually further from the most likely value than the optimistic one, so the average shifts toward the long side. This reflects that tasks run late more often than early.

Is the 95% range reliable?

It is a rough guide: two standard deviations around the mean, assuming a normal shape. The estimates themselves are the weak point; people tend to give ranges that are too narrow.