Planning a release needs an answer to a simple question: how many sprints are left? A team’s velocity, the points it finishes in each sprint, gives a data-based answer. This calculator averages your last three sprints, then divides the remaining backlog by that velocity, and also shows the best and worst cases, so that the forecast comes as a range and not as a promise.
How the calculation works
- Average velocity = sum of the last three sprints ÷ 3
- Sprints to finish = backlog ÷ average velocity, rounded up
- Best case = backlog ÷ best sprint, rounded up
- Worst case = backlog ÷ weakest sprint, rounded up
- Weeks = sprints × sprint length
Example
A team finished 34, 41 and 38 points in its last three two-week sprints, so its average velocity is 37.7 points. With 260 points left in the backlog, it needs 7 sprints, or 14 weeks. If the team repeats its best sprint, it still needs 7 sprints; if it repeats its weakest, it needs 8. The velocity varies by 18%, which is acceptable.
Why it matters
Forecasts based on measured velocity are more reliable than estimates made on a whiteboard, and they respond to what the team actually delivers. The range gives product owners and stakeholders an honest view of the schedule risk, so they can trade scope against dates.
Good to know
A forecast assumes that the backlog does not grow: new requests, rework and changes in scope extend the end date. Velocity is team-specific and depends on the estimation scale, so a change in team size or in how points are assigned breaks the comparison. Treat the result as a planning aid, not a commitment. This tool is for education.