The spare parts calculator gives the expected number of failures and the number of spares to stock so that the failures are covered with the confidence you choose, using the Poisson law.
How the calculation works
- Enter the number of units in service and the MTBF of one unit.
- Enter the period to cover and the confidence level.
- The calculator gives the expected failures, the spares to stock, the coverage reached, the coverage with one spare fewer and the risk of a stock-out.
Example
12 units with an MTBF of 8,000 h that run 8,760 h a year are expected to fail 12 × 8,760 / 8,000 = 13.14 times. To cover the failures with 95 % confidence, you need 19 spares: they cover 95.34 % of the cases, against 92.45 % with one spare fewer. The risk of a stock-out is 4.66 %.
Why it matters
The calculator helps maintenance planners, reliability engineers and small fleets owners to size a spare parts stock for pumps, motors, bulbs, drives or any part with random failures.
Good to know
Take the MTBF from the data sheet or, better, from your own failure records, because the catalog value is often optimistic. The period is the time you have to wait for a replenishment, not the year: if parts arrive in four weeks, cover four weeks of operation and reorder when you use a spare. A critical part with a long lead time deserves a higher confidence level, such as 99 %, while a cheap part can be covered at 90 %. If the units do not run all the time, use the running hours of the period. For a repairable part with a short repair loop, the stock can be much lower, so adjust the period to the repair time. The result is a number of whole parts and always rounds up.