The crane hoist reeving line pull and parts of line calculator gives the line pull at the drum, the minimum breaking force of the rope, the line speed and the power at the drum for a hoist with several parts of line, from the load, the sheave friction and the speed of the hook.
How the calculation works
- Enter the load on the hook, the parts of line and the friction factor of the sheaves.
- Enter the number of sheaves between the block and the drum, the hook speed, the efficiency and the design factor.
- The calculator finds the line pull, the minimum breaking force of the rope, the line speed and the power.
Example
A load of 20 tons is lifted with 6 parts of line, a friction factor of 1.04 and 8 sheaves before the drum. The line pull is 20 × 1.04^8 × 0.04 / (1.04^6 − 1) = 4.13 tons. With a design factor of 5, the rope needs a breaking force of 20.6 tons. At 30 ft/min of hook speed, the line speed is 180 ft/min, and the power at the drum is 53.0 hp with an efficiency of 0.85.
Why it matters
The calculator helps crane operators, riggers, equipment engineers and students to choose the number of parts of line for a load, to see the effect of the sheave friction, and to find the size of the rope and the power of the winch.
Good to know
Use the number of parts of line shown in the load chart of the crane, and reeve the rope as the manufacturer says. Keep the sheaves greased and the rope lubricated, and check the sheave grooves for wear. Replace the rope according to the standard, and do not exceed the rated line pull of the hoist.
Related tools
The wire rope capacity calculator gives the breaking force and the working load of a rope, the sling angle calculator gives the tension in the slings, the winch size calculator gives the line pull of a winch and the tower crane calculator checks the load moment of a lift.