Change order pricing calculator with markup tiers and time impact

Enter the labor, material, equipment, subcontract price, the markups, the bond and the time extension to get the total price of a change order and the effective markup.

Updated on
Your inputs
$

Value out of range

$

Value out of range

$

Value out of range

$

Value out of range

%

Value out of range

%

Value out of range

%

Value out of range

days

Value out of range

$

Value out of range

Results

Total price of the change order

55,143 $

Direct cost of the self-performed work
31,200 $
Markup on the work
5,305 $
Bond and insurance
588 $
Cost of the time impact
5,550 $
Effective markup on the direct cost
13.5 %

The change order pricing calculator gives the direct cost of the self-performed work, the markup with two tiers, the bond and insurance, the cost of the time impact, the total price and the effective markup.

How the calculation works

  • Enter the direct labor, material and equipment of the self-performed work and the subcontract price.
  • Enter the markups on the self-performed and the subcontracted work and the rate of bond and insurance.
  • Enter the time extension and its daily cost to get the total price of the change order.

Example

A change order has $18,400 of labor, $9,600 of material and $3,200 of equipment, so the self-performed direct cost is $31,200, and a subcontractor quotes $12,500. A markup of 15 % on the first part and 5 % on the subcontract adds $5,305. The bond and insurance of 1.2 % on the subtotal add $588.06. A time extension of 3 days at $1,850 per day adds $5,550. The total price is $55,143.06, an effective markup of 13.5 % on the direct costs.

Why it matters

The calculator helps contractors, subcontractors, owners and cost engineers to price or review a change order or an extra work proposal, to see how the markup tiers work and to check that the price follows the rules of the contract.

Good to know

Price the change from the detailed direct costs, with the burdened labor rates and the quotes of the subcontractors, and attach the backup. Apply only the markups that the contract allows, in the order that it states. Ask for the time extension and its cost in the same proposal when the change affects the critical path, and keep the schedule analysis with it. Record the date and the person who ordered the change, because work done on a verbal direction is the most common reason why a change order is disputed or paid late.

The markup calculator adds a margin to a cost, the overhead rate calculator spreads the fixed costs, the earned value calculator compares the work done with the plan and the PERT estimate calculator gives a duration with uncertainty.

Frequently asked questions

How is a change order priced?

A change order is priced from the direct cost of the added or changed work: the labor with its burden, the material, the equipment and the subcontractors. The contractor then adds the markup for overhead and profit that the contract allows, the bond and the insurance premium on the added amount, and any compensation for the time impact. The result is the amount that is added to the contract sum.

Why are there markup tiers?

Contracts often allow a higher markup on the work that the contractor does itself, such as 10 to 20 %, and a lower one on the work of subcontractors, such as 5 to 10 %, because the subcontractor has already included its own overhead and profit in the quote. The calculator takes the subcontract price as quoted and adds only the contractor's markup. The contract states the allowed rates and whether they compound.

How is the time impact priced?

If the change delays the work, the contractor can ask for a time extension, and for the general conditions costs of the extended period, such as site supervision, temporary facilities and insurance. The calculator multiplies the days by a daily cost. The delay must be shown with the schedule, and the home office overhead or the loss of productivity are usually claimed under separate rules of the contract.

What does the calculator leave out?

The calculator leaves out the pricing of deductive changes, the unit-price items, the escalation, the cost of preparing the proposal, the interest and the taxes on the added amount. It does not give legal advice, and the contract decides what can be charged, which markups apply and how the time is valued. Keep the backup for each cost, since the owner may audit the price of a change.