The change order pricing calculator gives the direct cost of the self-performed work, the markup with two tiers, the bond and insurance, the cost of the time impact, the total price and the effective markup.
How the calculation works
- Enter the direct labor, material and equipment of the self-performed work and the subcontract price.
- Enter the markups on the self-performed and the subcontracted work and the rate of bond and insurance.
- Enter the time extension and its daily cost to get the total price of the change order.
Example
A change order has $18,400 of labor, $9,600 of material and $3,200 of equipment, so the self-performed direct cost is $31,200, and a subcontractor quotes $12,500. A markup of 15 % on the first part and 5 % on the subcontract adds $5,305. The bond and insurance of 1.2 % on the subtotal add $588.06. A time extension of 3 days at $1,850 per day adds $5,550. The total price is $55,143.06, an effective markup of 13.5 % on the direct costs.
Why it matters
The calculator helps contractors, subcontractors, owners and cost engineers to price or review a change order or an extra work proposal, to see how the markup tiers work and to check that the price follows the rules of the contract.
Good to know
Price the change from the detailed direct costs, with the burdened labor rates and the quotes of the subcontractors, and attach the backup. Apply only the markups that the contract allows, in the order that it states. Ask for the time extension and its cost in the same proposal when the change affects the critical path, and keep the schedule analysis with it. Record the date and the person who ordered the change, because work done on a verbal direction is the most common reason why a change order is disputed or paid late.
Related tools
The markup calculator adds a margin to a cost, the overhead rate calculator spreads the fixed costs, the earned value calculator compares the work done with the plan and the PERT estimate calculator gives a duration with uncertainty.