The composite metal deck concrete volume and ponding calculator gives the average thickness of the slab, the volume of concrete, the volume with waste and the number of truckloads for a slab on a composite metal deck, with the fill of the ribs and the ponding by the deflection of the deck.
How the calculation works
- Enter the area of the deck, the concrete above the deck and the depth of the ribs.
- Enter the part of the ribs filled, the deflection of the deck, the ponding factor, the waste and the truck volume.
- The calculator finds the average thickness, the volume of concrete, the volume with waste and the truckloads.
Example
A deck of 12,000 ft² has 3.25 in of concrete above a 3 in rib, filled at 0.55, so the ribs add 3 × 0.55 = 1.65 in. The deck deflects 0.5 in under the wet concrete, and with a ponding factor of 0.70 this adds 0.35 in. The average thickness is 5.25 in, and the volume is 12,000 × 5.25 / 12 / 27 = 194.4 yd³. With 5 % of waste, the order is 204.2 yd³, that is 21 trucks of 10 yd³.
Why it matters
The calculator helps concrete contractors, estimators, steel erectors and students to estimate the concrete of a composite floor, to include the ponding that is often forgotten, and to plan the number of trucks of a pour.
Good to know
Measure the real deflection of the deck and of the beams before the pour and adjust the quantity. Consider shoring or a stronger deck if the ponding is large. Order the concrete with a margin for the first pour, and plan the pour sequence so that the deck is not overloaded by the piles of the concrete.
Related tools
The concrete volume calculator gives the volume of a pour, the slab joint spacing calculator gives the joints of a slab, the one-way slab minimum thickness calculator gives the thickness of a slab and the concrete formwork calculator estimates the forms.