Construction bid price build-up calculator

Enter the direct cost and the percentages for general conditions, contingency, overhead, profit and bond premium to get the bid price, the profit, the markup over cost and the margin on the price.

Updated on
Your inputs
$

Value out of range

% of direct cost

Value out of range

% of the subtotal

Value out of range

% of the subtotal

Value out of range

% of the subtotal

Value out of range

% of the bid price

Value out of range

Results

Bid price

2,529,922 $

Direct cost with general conditions
2,160,000 $
Subtotal with the contingency
2,224,800 $
Subtotal with the overhead
2,380,536 $
Subtotal with the profit
2,499,563 $
Profit in the price
119,027 $
Bond premium in the price
30,359 $
Markup over the direct cost
26.5 %
Profit margin on the bid price
4.7 %

The construction bid price calculator builds up the bid price of a project from the direct cost by adding the general conditions, the contingency, the overhead, the profit and the bond premium, and shows the markup over cost and the margin on the price.

How the calculation works

  • Enter the direct cost of the work and the percentages for the general conditions, the contingency, the overhead and the profit.
  • Enter the bond premium as a percent of the bid price.
  • The calculator adds each layer in turn and gives the bid price, the profit, the bond premium, the markup over the direct cost and the margin on the price.

Example

The direct cost is $2,000,000. General conditions of 8 % give $2,160,000. A 3 % contingency gives $2,224,800, 7 % of overhead gives $2,380,536 and 5 % of profit gives $2,499,563. A bond premium of 1.2 % of the price makes the bid price $2,499,563 / (1 − 0.012) = $2,529,922. The profit is $119,027, which is 4.7 % of the price, and the markup over the direct cost is 26.5 %.

Why it matters

The calculator helps estimators, contractors, subcontractors and owners to turn a takeoff into a price, to see how much each layer adds, to compare a bid with the cost of the work and to find the price that gives the profit you want.

Good to know

Apply each percent to the base that your company uses, since firms differ on whether the overhead and the profit apply to the direct cost or to the subtotal. Keep the general conditions as a list of items for the job and not only a percent, since a long job or a remote site raises them. Do not drop the contingency to win a bid without a reason. Check the margin on the price and not only the markup, because a markup of 15 % is a margin near 13 %. Add the sales tax and the escalation if the bid form wants them, and compare the final price with the budget of the owner.

The change order pricing calculator prices a change with tiered markups, the markup calculator gives the selling price from a cost, the overhead rate calculator allocates indirect costs and the earned value calculator tracks the cost and the schedule of the job.

Frequently asked questions

How is a bid price built up?

A contractor adds the indirect items in layers to the direct cost of the work: the general conditions of the job (site staff, trailers, temporary works), a contingency for risk, the overhead of the home office and the profit. If a performance and payment bond is required, its premium, a percent of the contract price, is added at the end.

Why is the bond divided and not multiplied?

The premium is a percent of the contract price, which includes the premium itself. If the premium is 1.2 % of the price, the price before the bond is 98.8 % of it, so the price is the subtotal divided by (1 − 0.012). Multiplying the subtotal by 1.012 would give a premium of slightly less than 1.2 % of the price.

What is the difference between markup and margin?

Markup is the percent added on the cost, and margin is the profit as a percent of the price. A profit of 5 % added on the cost is a margin of 4.8 % on the price, because the price is larger than the cost. Be sure which one a target or a competitor means, and the calculator shows both.

What does the calculator leave out?

The calculator leaves out the sales tax, the taxes on the contract, the escalation over the length of the job, the retainage and the financing cost, the cost of insurance that is not in the general conditions, and the allowances of the owner. Put each of them in a layer or in the direct cost as the bid form requires.