The earthwork overhaul calculator gives the overhaul distance beyond the free haul, the overhaul quantity in station-yards, the overhaul cost, the cost of the excavation with the free haul and the average cost per cubic yard.
How the calculation works
- Enter the volume hauled, the average haul distance from the center of the cut to the center of the fill, and the free haul distance.
- Enter the unit price of excavation with the free haul and the unit price of overhaul per station-yard.
- The calculator gives the overhaul distance, the overhaul quantity, the costs and the average cost per cubic yard.
Example
18,000 yd³ are hauled over an average distance of 1,450 ft with a free haul of 500 ft. The overhaul distance is 950 ft, that is 9.5 stations, so the overhaul is 18,000 × 9.5 = 171,000 station-yd³. At $0.20 per station-yard it costs $34,200. The excavation with the free haul at $4.00/yd³ costs $72,000. The total is $106,200, an average of $5.90/yd³.
Why it matters
The calculator helps estimators, civil engineers, earthwork contractors and inspectors to price the haul of a cut to a fill, to check an overhaul quantity of a pay item, and to see how much the free haul distance changes the cost.
Good to know
Check the definition of the free haul and of the station-yard in the specification, since some contracts use a free haul of 1,000 ft or measure the haul along the haul road and not along the straight line. Use the volume as the contract measures it, in bank yards or in compacted yards. Compare the overhaul with the cost of a nearby borrow pit and a waste site, since it can be cheaper than a long haul.
Related tools
The earthwork swell and shrink calculator converts the volumes of soil, the haul truck rimpull calculator checks the grade a truck can climb, the scraper cycle production calculator gives the production of scrapers and the dump truck loads calculator gives the loads to haul a volume.