Retainage and progress payment application calculator

Enter the contract sum, the percent complete, the stored materials, the payments already certified and the retainage rates to get the net payment of the period.

Updated on
Your inputs
$

Value out of range

%

Value out of range

$

Value out of range

$

Value out of range

%

Value out of range

%

Value out of range

%

Value out of range

Results

Net payment this period

155,150 $

This is the amount to pay for the period
Gross value earned to date
1,437,000 $
Retainage held to date
131,850 $
Effective retainage rate
9.18 %
Net amount due to date
1,305,150 $

The retainage and progress payment calculator gives the gross value earned, the retainage held with a rate reduction at a threshold, the net amount due to date and the net payment of the period of a construction contract.

How the calculation works

  • Enter the contract sum, the percent complete and the stored materials billed to date.
  • Enter the net payments already certified and the retainage rates with the threshold where the rate changes.
  • The calculator gives the gross value earned, the retainage held, the net due to date and the net payment of the period.

Example

A contract of $2,400,000 is 58 % complete, with $45,000 of stored materials. The gross value to date is $1,437,000. Retainage is 10 % of the first 50 % of the contract, or $1,200,000, and 5 % above it, so $131,850 is held, an effective rate of 9.18 %. The net amount due to date is $1,305,150. After the $1,150,000 already certified, the payment of the period is $155,150.

Why it matters

The calculator helps contractors, subcontractors, owners and project accountants to prepare or check a payment application, to see how much is held back and for how long, and to plan the cash flow of a project.

Good to know

Match the percent complete with the schedule of values of the contract, and keep the previous certified amounts from the earlier applications. Check the retainage rule of each subcontract, because it often differs from the prime contract. Track the retainage as a separate account, since it is both a receivable for the contractor and a liability for the owner, and ask for its release in writing at the right milestone. Keep copies of the lien waivers, the certified payroll and the insurance certificates that the owner requires with each application, because a missing document delays the payment of the whole period.

The earned value calculator compares the work done with the plan, the equipment owning and operating cost calculator gives the hourly cost of a machine, the markup calculator adds a margin to a cost and the overhead rate calculator spreads the fixed costs.

Frequently asked questions

What is retainage?

Retainage, or retention, is a share of each progress payment that the owner holds back until the work is complete, to make sure the contractor finishes the work and corrects defects. It is commonly 5 to 10 % of the value earned. Many contracts reduce the rate or stop retaining once the work is a given percentage complete, for example after 50 %, if the progress is satisfactory. Local law limits the rate in some places.

How is the payment calculated?

The gross value earned to date is the contract sum times the percent complete, plus the stored materials billed. The retainage is the rate times the gross value, using the lower rate on the part above the threshold. The net amount due to date is the gross value less the retainage. The payment of the period is this net amount less the net payments already certified in the earlier applications.

When is retainage released?

The release depends on the contract. It is often paid in full at substantial completion or final completion, sometimes less a sum for the punch-list items, often 150 % of their value. Some contracts release part of it at milestones. The retainage held at any time is in the calculator, and it is also the amount that a subcontractor waits for, which is why the terms flow down to the subcontracts.

What does the calculator leave out?

The calculator uses one retainage rule, and it leaves out the interest on the retainage, the bond or other security that replaces it, the separate treatment of stored materials, the deductions for back-charges and the taxes. It does not give legal advice. The contract, the law of the place and the architect's or engineer's certificate decide the amounts, so check them before you issue or pay an application.

Was this calculator helpful?

Thanks for your feedback!

Results are estimates provided for information purposes. They do not replace professional advice.