Shotcrete calculator: how much shotcrete to order with the rebound loss

Enter the area, the thickness, the irregularity allowance, the rebound loss and the nozzle output to get the volume in place, the volume to order, the rebound waste and the spraying time.

Updated on
Your inputs
ft²

Value out of range

in

Value out of range

%

Value out of range

yd³/h

Value out of range

Results

Volume to order (with the rebound)

17.75 yd³

Design volume in place
12.35 yd³
Volume in place with the irregularity
14.20 yd³
Rebound that falls to the ground
3.55 yd³
Spraying time
2.96 h

The shotcrete calculator gives the volume in place, the volume to order with the rebound, the rebound that falls to the ground and the spraying time for a wall, a slope or a tunnel lining, from the area, the thickness, the irregularity, the rebound loss and the nozzle output.

How the calculation works

  • Enter the area to be sprayed and the design thickness of the shotcrete.
  • Enter the allowance for the irregularity of the surface, choose the rebound that fits the process and the position, and enter the nozzle output.
  • The calculator finds the volume in place, the volume to order with the rebound, the rebound that falls to the ground and the spraying time.

Example

A wall of 1,000 ft² is sprayed with a design thickness of 4 in, which is 1,000 × 4 / 12 / 27 = 12.35 yd³ in place. With an allowance of 15 % for the irregularity, the volume in place is 14.20 yd³. With a rebound of 20 %, the volume to order is 14.20 / (1 − 0.20) = 17.75 yd³, and 3.55 yd³ falls to the ground. At a nozzle output of 6 yd³/h, the spraying takes 2.96 h.

Why it matters

The calculator helps shotcrete contractors, tunnel and slope engineers, estimators and students to order the right quantity of material, to estimate the cost of the waste and to plan the time of the spraying for a shoring wall, a rock support or a repair.

Good to know

Order the volume with the rebound but control the waste: use a well-trained nozzleman, keep the nozzle at the right distance and angle, and choose a mix designed for shotcrete with enough fines. Spray the corners and the mesh in thin passes, remove the rebound and the overspray from the work, and check the thickness with depth gauges or test panels during the work.

The tunnel rock support Q-system calculator rates the rock mass and suggests the support, the concrete volume calculator gives the quantity for a shape, the excavation calculator gives the volume of the cut and the soil nail pullout calculator checks the soil nails behind the shotcrete facing.

Frequently asked questions

What is the rebound of shotcrete?

The rebound is the part of the material that bounces off the surface and falls to the ground instead of staying in place. It is mostly the coarse aggregate that does not stick in the paste at the start. The rebound depends on the process, wet or dry, the position of the nozzle, the mix, the air pressure and the skill of the nozzleman, and it is a waste that must be removed and not reused in the work.

What rebound values are used?

The guide ACI 506 gives a rebound of about 5 to 15 % for a wet mix on walls and floors and 15 to 25 % for the wet mix overhead, and 15 to 30 % for the dry mix on walls and 25 to 50 % overhead. The values in the calculator are rounded values in these ranges. Use the data of the contractor and the results of the test panels when they are available.

Why is an irregularity allowance needed?

A rock face, a soil nail wall or an old concrete wall is never flat, so the real thickness is more than the design thickness in the low parts. The allowance of 10 to 30 % is common for a rock surface, and the volume must also include the filling of the overbreak of the excavation. The survey of the surface before spraying gives a better estimate.

What are the limits of the calculator?

The calculator uses a uniform thickness and a constant rebound. It does not include the reinforcement and the mesh that increase the rebound, the waste at the start and the end of the day, the volume left in the hose and the pump, the accelerator, the tolerance of the delivery or the time to move the equipment. Order a bit more for the first day of a job, because the rebound is usually higher.