The temporary power calculator gives the connected load, the demand load, the apparent power in kVA, the line current and the generator or service size of a construction site, from the loads, the demand factor, the power factor and the voltage.
How the calculation works
- Enter the connected loads of the offices, the lighting, the hoists, the tools and the other equipment.
- Enter the demand factor, the power factor, the supply voltage and the reserve for growth and motor starting.
- The calculator finds the demand load, the apparent power, the line current and the generator or service size.
Example
A site has 12 + 8 + 30 + 25 + 15 = 90 kW of connected load. With a demand factor of 0.70, the demand is 63.0 kW, which is 63 / 0.85 = 74.1 kVA at a power factor of 0.85. At 480 V three-phase, the line current is 74,118 / (1.732 × 480) = 89.1 A. With a 25 % reserve, the generator or the service must be at least 92.6 kVA.
Why it matters
The calculator helps site managers, electrical contractors, estimators and students to size the temporary power or the generator of a job, to compare the cost of a generator and of a temporary service, and to check the current in the feeder of the site.
Good to know
Keep a list of the loads of the site and update it when new equipment arrives. Use ground-fault protection on all the outlets of the site, protect the cables from the traffic and from the water, and keep the generator ventilated and away from the air intakes. Check the voltage at the end of the long feeders, and balance the single-phase loads over the three phases.
Related tools
The generator size calculator sizes a standby generator, the transformer calculator sizes the transformer of a temporary service, the conduit fill calculator checks the conduits and the voltage regulation calculator checks the voltage at the end of a feeder.