Trench pipe laying calculator: daily production and cost of a pipe crew

Enter the section length, the times of excavation, bedding, laying and backfill, the efficiency, the hours, the crew cost and the job length to get the production per day, the days and the cost per foot.

Updated on
Your inputs
ft

Value out of range

min

Value out of range

min

Value out of range

min

Value out of range

min

Value out of range

min

Value out of range

h

Value out of range

$/h

Value out of range

ft

Value out of range

Results

Production per day

267 ft/day

Time per pipe section
30 min
Sections installed per day
13.3
Days for the job
7.5 days
Cost per foot of pipe
10.50 $/ft

The trench pipe laying calculator gives the time per pipe section, the sections per day, the production per day, the days for the job and the cost per foot of pipe for a pipe crew in a trench, from the length of the sections, the times of the operations, the efficiency and the cost of the crew.

How the calculation works

  • Enter the length of a pipe section and the time needed for the excavation, the bedding, the laying and the backfill of one section.
  • Enter the working time per hour, the hours worked per day, the cost of the crew and the length of the job.
  • The calculator finds the time per section, the sections per day, the production per day, the days for the job and the cost per foot.

Example

A crew lays pipe sections of 20 ft. A section needs 8 min to dig, 4 min for the bedding, 10 min to lay and join and 8 min to backfill, so the cycle is 30 min. In 8 h with 50 min of work per hour, the crew installs 8 × 50 / 30 = 13.3 sections, or 13.3 × 20 = 267 ft/day. A job of 2,000 ft takes 7.5 days. With a crew cost of $350/h, the cost is 350 × 8 / 266.7 = $10.50 per foot.

Why it matters

The calculator helps utility contractors, estimators, project managers and students to estimate the schedule and the labor cost of a water, sewer or drainage pipeline, to compare crews and to see how the length of the pipe and the cycle time change the daily production.

Good to know

Record the real times of each operation on a few sections at the start of the job and update the estimate. Keep the excavation ahead of the laying, backfill as soon as the pipe is tested to keep the trench open as short as possible, and plan the delivery of the pipe and of the bedding material. Add time for the manholes, the crossings and the tests of the pipe, which are not in the cycle.

The excavation calculator gives the volume of the trench, the pipe volume calculator gives the volume of the pipe, the labor productivity calculator gives the work output of the crew and the trench dewatering wellpoints calculator handles the groundwater.

Frequently asked questions

How is the production of a pipe crew calculated?

The crew works in a repeated cycle for each pipe section: the excavation of the trench, the placing of the bedding, the laying and the joining of the pipe, and the backfilling and the compaction. The production per day is the working time of the day divided by the cycle, times the length of the section. When the operations are done by different machines in a sequence, the slowest operation can limit the production.

How can the production be increased?

The production grows when the cycle is shorter or when the operations are done in parallel by separate crews, for example an excavator that digs ahead and a laying crew that follows. A trench box, a longer section of pipe, a good bedding material and a short distance between the stockpile and the trench also help. The depth of the trench, the soil and the water change the times a lot.

What does the cost per foot include?

The cost per foot is the hourly cost of the crew and of the equipment times the hours of the day, divided by the length laid per day. It does not include the pipe, the bedding material, the fittings, the testing, the paving or the traffic control, which are added to the unit price of the job.

What are the limits of the calculator?

The calculator uses constant times per section and no interruptions. It does not include the manholes, the fittings, the crossings of the utilities, the rock, the groundwater, the shoring, the weather, the testing of the pipe or the restoration of the surface. The times of the cycle should come from the records of similar jobs, and a contingency should be added to the days of the job.