Pipe trench bedding and backfill calculator: excavation, bedding and backfill

Enter the pipe diameter, the trench width and length, the cover, the bedding thicknesses, the allowance and the density to get the excavation, the bedding, its weight and the backfill.

Updated on
Your inputs
in

Value out of range

ft

Value out of range

in

Value out of range

in

Value out of range

ft

Value out of range

ft

Value out of range

%

Value out of range

tons/yd³

Value out of range

Results

Bedding to order

168.3 yd³

Excavation
367.3 yd³
Weight of the bedding
227.3 tons
Native backfill above the bedding
194.4 yd³

The pipe trench bedding and backfill calculator gives the excavation, the bedding to order, the weight of the bedding and the native backfill of a buried pipe, from the pipe diameter, the trench size and the thickness of the bedding.

How the calculation works

  • Enter the outside diameter of the pipe, the trench width, the length and the depth of cover over the pipe.
  • Enter the bedding thickness under the pipe, the bedding above the top of the pipe, the allowance and the density of the bedding.
  • The calculator finds the excavation, the bedding to order, the weight of the bedding and the native backfill.

Example

A trench 500 ft long and 3.5 ft wide holds a pipe of 14 in with 4 ft of cover, 6 in of bedding under it and 12 in above it. The trench is 4 + 14/12 + 6/12 = 5.67 ft deep, so the excavation is 367.3 yd³. The bedding zone is 2.67 ft high, and after the volume of the pipe is removed, the bedding with a 10 % allowance is 168.3 yd³, or 227.3 tons at 1.35 tons/yd³. The native backfill above the bedding is 3.0 ft thick and makes 194.4 yd³.

Why it matters

The calculator helps utility contractors, estimators, inspectors and students to estimate the quantities of excavation, bedding and backfill of a sewer, a water main or a drain, to order the right tons of bedding material, and to compare several trench widths or bedding thicknesses.

Good to know

Build the trench with a width that gives room to compact the bedding on the sides of the pipe, and shape the bottom of the bedding to support the pipe on its lower part. Compact the bedding in layers, not with a dump, and keep the stones larger than the limit away from the pipe. Check the grade of the bedding before the pipe is placed, and the cover after the backfill.

The trench pipe laying production calculator plans the laying of the pipe, the buried pipe earth load calculator gives the load on the pipe, the earthwork swell and shrink calculator gives the volumes of soil to haul and the soil compaction calculator checks the density of the backfill.

Frequently asked questions

What is the bedding of a pipe?

The bedding is the layer of selected granular material, such as sand or crushed stone, placed under, around and over a buried pipe. It gives the pipe a uniform support, spreads the load of the soil above and protects the pipe from sharp stones. The type and the thickness of the bedding are given by the specification and depend on the type of pipe, the depth and the soil.

How are the volumes found?

The excavation is the depth of the trench times its width and its length. The bedding zone is the height from the bottom of the bedding to the top of the bedding above the pipe, times the width and the length, minus the volume of the pipe itself. The native backfill is the part of the cover above the bedding. The bedding volume has an allowance for the compaction and for the loss in the trench.

Why is the weight of the bedding given?

The bedding is bought and delivered by weight, so the volume of the bedding is multiplied by its density to get the tons to order. The density depends on the material and on the moisture, and it is about 1.35 tons/yd³ for a loose sand or a crushed stone in the place and 1.7 t/m³ in the compacted state. Use the value given by the supplier for the real material.

What are the limits of the calculator?

The calculator gives the volumes for a trench with vertical sides and a constant section. It does not include the extra width of a sloped trench or of a trench box, the manholes and the fittings, the swell of the excavated soil, the removal of the surplus soil, the trench bottom that is overdug, the rock excavation or the sheeting. The width of the trench must also follow the minimum and maximum widths of the specification.

Was this calculator helpful?

Thanks for your feedback!

Results are estimates provided for information purposes. They do not replace professional advice.