Why does work take so long when everyone is busy? Little’s law gives a simple link between three numbers: the work in progress, the throughput and the cycle time. When a team starts more than it finishes, items wait, and the average time grows. This calculator gives the cycle time from the WIP and throughput, and the WIP limit needed to reach a target.
How the calculation works
- Cycle time = work in progress ÷ throughput
- WIP limit = throughput × target cycle time
- Items to remove = current WIP − WIP limit
Example
A team has 24 items in progress and finishes 8 per week. The average cycle time is 3 weeks, or 15 working days. To get the average to 2 weeks, the WIP limit is 16, which means 8 items must be finished or removed before new ones start.
Why it matters
Little’s law underlies kanban and lean practice. It explains why limiting work in progress shortens delivery without asking anyone to work faster, and it holds for support queues, factory floors, hospital wards and server requests. It is also a quick consistency check: if reported figures for the three quantities do not fit, one of them is wrong.
Good to know
The law relates averages in a stable system. If the team’s throughput changes sharply, or the backlog grows rapidly, the equation holds only over long periods. Average cycle time hides spread: some items take far longer than average, and percentiles are better to promise delivery dates. Keep the units consistent: if throughput is per week, the cycle time comes out in weeks. The law says nothing about the order in which items are handled, so it should be combined with good prioritization, and it does not tell you how to raise the throughput itself; reducing WIP mainly removes waiting. This tool is for education.