At the current pace, will the work finish on time?

Enter the total scope, the points completed, the days elapsed and the days planned: get the projected duration, the days late, the points behind and the pace needed.

Updated on
Your inputs

Value out of range

Value out of range

Value out of range

Value out of range

Results

Projected total duration (working days)

13.3

At this pace, the work will overrun the plan by more than 15%
Days late (+) or early (−) compared with the plan
3.3
Points remaining
66
Points behind (+) or ahead (−) of the ideal burndown
18.0
Pace needed to finish on time (points per day)
16.5
Current pace (points per day)
9.00

Halfway through a sprint, the question is not how much is done but whether the team will finish on time. A burndown compares the work remaining with an ideal line that falls steadily to zero. This calculator turns your numbers into a projection: the total duration at the current pace, the days of delay, the points behind the ideal line and the pace needed to finish on time.

How the calculation works

  • Current pace = points completed ÷ days elapsed
  • Projected duration = total scope ÷ current pace
  • Ideal remaining = scope × (1 − days elapsed ÷ days planned)
  • Points behind = actual remaining − ideal remaining
  • Pace needed = points remaining ÷ days left

Example

A project has 120 points to deliver in 10 working days. After 6 days, 54 points are done, so the pace is 9 points per day. At that rate the work takes 13.3 days, 3.3 more than planned. The ideal burndown would have 48 points left, and the actual figure is 66, which is 18 points behind. To finish on time, the team needs 16.5 points per day, nearly twice the current pace.

Why it matters

A sprint review that comes too late cannot change anything. Checking the projection in the middle of the sprint leaves time to cut scope, ask for help or warn stakeholders. It also puts a number on the effort needed to recover, which helps the team judge whether the target is realistic.

Good to know

Work seldom burns down in a straight line: it is often slow at the beginning, when tasks are being started, and faster at the end. A linear projection is therefore pessimistic early in a sprint and optimistic late. Points are relative estimates, and the result is only as good as they are. This tool is for education.

The sprint velocity calculator forecasts the number of sprints in a backlog, the team capacity calculator estimates what a sprint can hold, and the earned value calculator measures cost and schedule performance.

Frequently asked questions

What is a burndown chart?

A chart of the work remaining over time. The ideal line goes from the total scope at the start to zero at the end; the actual line shows what is left each day. When the actual line is above the ideal one, the team is behind.

How is the projected finish estimated?

By assuming the pace so far continues: the total scope divided by the points completed per day. It is a linear extrapolation, so it ignores changes in speed that usually come with the end of a sprint or a release.

What if the scope changes during the sprint?

Enter the new total scope. Added work lengthens the forecast, and removed work shortens it. Frequent changes in scope make a burndown hard to read and are worth discussing with the team.

Why compare with the pace needed?

Because it shows the effort required to recover. If the pace needed is far above the current one, the team has to cut scope, add capacity or move the date.