A building or an embankment on soft clay can keep sinking for years after it is finished. The consolidation settlement calculator takes the layer thickness, the void ratio, the compression index, the stress before and after loading, the coefficient of consolidation and the drainage, and gives the primary settlement, the strain, the final void ratio and the times for 50 % and 90 % consolidation.
How the calculation works
- Enter the thickness of the clay layer, its initial void ratio and its compression index Cc, from a consolidation test.
- Enter the effective stress at the middle of the layer before loading and the stress increase from the new load.
- The settlement is Sc = Cc × H / (1 + e₀) × log₁₀((σ’₀ + Δσ) / σ’₀), for a normally consolidated clay.
- Enter the coefficient of consolidation and the drainage to get the time: t = Tv × Hdr² / cv, with Tv = 0.197 for 50 % and 0.848 for 90 % consolidation.
Example
A clay layer is 10 ft thick, with e₀ = 0.9 and Cc = 0.30. The effective stress at mid-layer is 1,500 psf and a new load adds 1,000 psf. The settlement is 0.30 × 10 / 1.9 × log₁₀(2,500 / 1,500) = 0.350 ft, or 4.20 in, a strain of 3.50 %. The void ratio falls to 0.833. With sand above and below, the drainage path is 5 ft, and with cv = 0.1 ft²/day, 50 % consolidation takes 49.3 days and 90 % takes 212 days.
Why it matters
Total settlement and differential settlement decide whether a structure cracks, whether a road needs repaving and how long you must wait before building on a preloaded site. Computing the settlement and the time lets you compare options such as preloading, vertical drains, lighter fill or deep foundations before the first test pit is dug.
Good to know
The calculator treats the layer as one homogeneous, normally consolidated clay with the stress taken at mid-layer, and one-dimensional compression under a wide load. Thick layers should be split into sublayers, narrow footings spread the stress with depth, and secondary compression (creep) comes on top of the primary settlement. Use parameters from site tests and treat the result as a first estimate.