The contour interpolation calculator gives the elevation of a point between two spot elevations, the slope between them and the distance from the first point at which a contour elevation crosses the line.
How the calculation works
- Enter the elevations of the two known points and the horizontal distance between them.
- Enter the distance from point 1 to the new point and, if you want a contour, the target elevation.
- The calculator gives the elevation of the new point, the slope, the run for 1 ft of rise and the distance to the target elevation.
Example
Two spot elevations are 100 ft and 105 ft, 62 ft apart. A point 24 ft from the first has an elevation of 100 + 5 × 24 / 62 = 101.935 ft. The slope is 5 / 62 = 8.065 %, which is 12.4 ft of run for each foot of rise. The 102 ft contour crosses the line at 2 × 62 / 5 = 24.8 ft from the first point.
Why it matters
The calculator helps surveyors, civil engineers, site planners, landscapers and students to read a grading plan, to find the elevation of a stake between contours and to locate the line of a contour on the ground.
Good to know
Use the horizontal distance between the points, not the distance along the ground, and put the elevations in the same datum and unit. Interpolate along a line where the ground slopes evenly, and add a point wherever the ground changes its slope, such as at a ditch or a ridge. To place a contour, enter its elevation as the target elevation, and repeat the calculation for each pair of spot elevations that the contour crosses. For design grades, round the result to the precision of the plan and check the slope against the limits of the project.