Dust control water truck calculator: water demand of a haul road

Enter the length and the width of the road, the water rate, the passes per day and the truck capacity to get the area wetted, the water per pass, the water per day and the truck loads.

Updated on
Your inputs
ft

Value out of range

ft

Value out of range

gal/yd²

Value out of range

Value out of range

gal

Value out of range

Results

Water per day

33,333 gal

Area wetted by one pass
16,667 yd²
Water for one pass
4,167 gal
Truck loads per day
8.3

The dust control water truck calculator gives the area wetted, the water for one pass, the water per day and the number of truck loads needed to control the dust on a haul road or a construction site road, from its size, the rate of water and the number of passes.

How the calculation works

  • Enter the length and the width of the haul road to wet.
  • Enter the water rate of one pass, the passes per day and the capacity of the water truck.
  • The calculator finds the area wetted, the water for one pass, the water per day and the truck loads per day.

Example

A haul road 5,000 ft long and 30 ft wide has an area of 5,000 × 30 / 9 = 16,667 yd². At 0.25 gal/yd² per pass, one pass takes 4,167 gal. With 8 passes a day, the road needs 33,333 gal per day, which is 8.3 loads of a 4,000 gal water truck.

Why it matters

The calculator helps site managers, earthwork contractors, quarry supervisors and students to plan the water supply for dust control, to size the water truck and the source of water, and to estimate how the number of passes changes the water demand of the day.

Good to know

Water the road before the dust is visible and keep the surface slightly damp, not wet. Increase the passes in hot and windy weather, reduce the speed of the trucks, which reduces the dust a lot, and keep the road well graded to avoid loose material. Check the spray bar and the pump of the truck, and measure the real rate by timing a pass on a known length.

The haul truck rimpull and grade calculator checks the trucks on a ramp, the dozer production blade calculator sizes the earthmoving, the motor grader blading production calculator plans the grading of the road and the earthwork swell and shrink calculator gives the volumes of soil.

Frequently asked questions

Why control the dust on a haul road?

The trucks and the equipment raise a lot of dust on an unpaved haul road, which reduces the visibility, harms the health of the workers and the neighbors, wears the machines and can break the rules of air quality. Watering the road is the most common way to control the dust on a construction site, a quarry or a mine, and it is often required by the permit of the site.

What is a usual water rate?

The usual rate is from 0.1 to 0.5 gal/yd², or 0.5 to 2 L/m², for each pass. A rate that is too light evaporates in a short time and does not control the dust, and a rate that is too heavy makes the road muddy and slippery. In hot and dry weather the road needs more passes, and a binder or a chemical suppressant can reduce the number of passes.

How often must the road be watered?

The frequency depends on the weather, the traffic and the material of the road. On a hot and windy day with many trucks, the road can dry in one or two hours, so that eight passes in a work day is a common value. The calculator uses the number of passes that you enter, and you can adjust it after you have seen how the road behaves.

What are the limits of the calculator?

The calculator gives the water demand with the area, the rate and the number of passes. It does not include the time of the truck to fill and to travel to the water point, the loss of the water by the spray bar, the water used for the compaction or the rate of evaporation. The number of trucks needed depends on the cycle time, which depends on the distance to the water source.