The dozer production calculator gives the cycle time, the cycles per hour and the production in loose and bank volume of a bulldozer pushing soil, from the blade capacity, the push distance, the speeds, the grade and the swell.
How the calculation works
- Enter the blade capacity, the push distance and the forward and reverse speeds of the dozer.
- Enter the fixed time, the working minutes per hour, the grade of the push and the swell of the material.
- The calculator finds the cycle time, the cycles per hour and the production in loose and in bank volume.
Example
A dozer with a blade of 8 yd³ pushes the soil over 150 ft, going at 2 mph loaded (176 ft/min) and back at 3.5 mph (308 ft/min). The cycle is 150 / 176 + 150 / 308 + 0.3 = 1.64 min. With 50 min of work per hour, there are 50 / 1.64 = 30.5 cycles per hour. A push uphill of 5 % gives a grade factor of 1 − 0.02 × 5 = 0.90, so the loose production is 8 × 30.5 × 0.90 = 220 yd³/h. With a swell of 25 %, the bank production is 176 yd³/h.
Why it matters
The calculator helps earthwork estimators, site managers, equipment planners and students to estimate the output of a dozer in clearing, stripping and spreading, to compare the push distances and to match the dozer with the loaders and the trucks of the job.
Good to know
Use the real blade capacity of the machine, the push distance measured on the plan and a realistic efficiency of 45 to 50 minutes per hour. Push downhill when possible, and keep the cut and fill balanced to shorten the distances. For long distances over about 300 ft, compare the cost with a scraper or an excavator and trucks, which are more economical.
Related tools
The earthwork swell and shrink calculator converts the bank, loose and compacted volumes, the excavation calculator gives the volume to move, the haul truck calculator checks the trucks on a grade and the excavator productivity calculator estimates a machine that loads the trucks.