The liquidated damages calculator gives the days of delay after the time extensions, the damages charged with the cap, their share of the contract, any early completion bonus and the net adjustment to the contract sum.
How the calculation works
- Enter the contract duration, the time extensions granted and the actual duration to completion.
- Enter the damages per day, the bonus per day if any, the contract sum and the cap.
- The calculator gives the days of delay, the liquidated damages, their share of the contract and the net adjustment.
Example
A contract has a duration of 365 days, and 12 days of extensions were granted, so the allowed duration is 377 days. The work took 398 days, a delay of 21 days. At $2,500 per day, the liquidated damages are $52,500, which is 1.25 % of the $4,200,000 contract and well below the 10 % cap. With no early bonus, the net adjustment is −$52,500.
Why it matters
The calculator helps contractors, owners, project managers and claims staff to put a number on a delay, to see the effect of the time extensions and of the cap, and to prepare for a discussion of the completion date.
Good to know
Keep a log of the delay events and the notices from the first day, because the extensions are won with records. Check that the damages clause, the cap and the unit of days match the contract, and see whether the bonus applies. Compare the amount with the cost of accelerating the work, which is sometimes smaller than the damages. Ask for the extension in writing within the notice period of the contract, with the schedule that shows the effect of the event on the critical path, because a late notice can lose a right that is otherwise valid.