Liquidated damages and delay days calculator for a construction contract

Enter the contract duration, the extensions, the actual duration, the daily damages, the bonus, the contract sum and the cap to get the days of delay and the damages.

Updated on
Your inputs
days

Value out of range

days

Value out of range

days

Value out of range

$

Value out of range

$

Value out of range

$

Value out of range

%

Value out of range

Results

Liquidated damages charged

52,500 $

Contract duration with the extensions
377 days
Days of delay
21 days
Damages as a share of the contract
1.25 %
A small amount compared with the contract
Days finished early
0 days
Early completion bonus
0 $
Net adjustment to the contract sum
-52,500 $

The liquidated damages calculator gives the days of delay after the time extensions, the damages charged with the cap, their share of the contract, any early completion bonus and the net adjustment to the contract sum.

How the calculation works

  • Enter the contract duration, the time extensions granted and the actual duration to completion.
  • Enter the damages per day, the bonus per day if any, the contract sum and the cap.
  • The calculator gives the days of delay, the liquidated damages, their share of the contract and the net adjustment.

Example

A contract has a duration of 365 days, and 12 days of extensions were granted, so the allowed duration is 377 days. The work took 398 days, a delay of 21 days. At $2,500 per day, the liquidated damages are $52,500, which is 1.25 % of the $4,200,000 contract and well below the 10 % cap. With no early bonus, the net adjustment is −$52,500.

Why it matters

The calculator helps contractors, owners, project managers and claims staff to put a number on a delay, to see the effect of the time extensions and of the cap, and to prepare for a discussion of the completion date.

Good to know

Keep a log of the delay events and the notices from the first day, because the extensions are won with records. Check that the damages clause, the cap and the unit of days match the contract, and see whether the bonus applies. Compare the amount with the cost of accelerating the work, which is sometimes smaller than the damages. Ask for the extension in writing within the notice period of the contract, with the schedule that shows the effect of the event on the critical path, because a late notice can lose a right that is otherwise valid.

The earned value calculator compares the progress with the plan, the PERT estimate calculator gives a duration with uncertainty, the labor productivity calculator measures the output of a crew and the markup calculator adds a margin to a cost.

Frequently asked questions

What are liquidated damages?

Liquidated damages are a sum per day, agreed in the contract, that the contractor pays the owner when the work is finished after the completion date. They are a pre-agreed estimate of the owner's loss, such as lost rent, extra financing and extended supervision, so the owner does not have to prove the actual loss. To be enforceable, the amount must be a reasonable forecast of the loss and not a penalty.

How are the days of delay counted?

The contract duration is extended by the time extensions that the contractor is entitled to, for example for owner-caused changes, unusual weather or other excusable delays. The delay is the actual duration less the extended duration, and it is never negative. Depending on the contract, the days are calendar days or working days, and the calculator counts the days in the unit that you enter.

What does the cap do?

Many contracts limit the total liquidated damages to a share of the contract sum, commonly 5 to 10 %, or to another fixed amount. The calculator charges the smaller of the daily damages times the days of delay and the cap. A contract can also provide an incentive for early completion, which is the bonus per day times the days finished before the extended completion date.

What does the calculator leave out?

The calculator leaves out the concurrent delays, the proof of the extensions, the notice rules, the waiver of the damages, the partial occupancy and the separate milestones that some contracts have. It also does not decide if the clause is enforceable. It does not give legal advice, so use the contract and the advice of your lawyer or contracts manager for a claim or a dispute.