Workable days and weather delay calculator

Enter the workdays needed, the working days per week and the normal adverse weather days per month to get the workable days, the calendar duration and the lost workdays beyond normal weather.

Updated on
Your inputs
days

Value out of range

Value out of range

days

Value out of range

days

Value out of range

Results

Calendar days to finish

201 days

Workable days per month
18.1 days
Months to finish
6.6 months
Calendar days without any weather
168 days
Expected workdays lost to normal weather
23.6 days
Workdays lost beyond normal weather
4.4 days
Weather worse than normal: a time extension may be claimed if the contract allows it

The workable days calculator gives the workable days per month, the calendar days to finish an activity with the normal adverse weather, and the workdays lost beyond normal that can justify a schedule extension.

How the calculation works

  • Enter the workdays that the activity needs, the working days per week and the normal adverse weather days per month of the season.
  • Enter the workdays actually lost to weather if the job is under way.
  • The calculator gives the workable days per month, the months and calendar days to finish, the weather delay and the workdays lost beyond normal.

Example

An activity needs 120 workdays, on a 5 day week, and the weather normally stops work on 5 days per month. Only 5 / 7 of those days fall on a workday, so there are 5/7 × (30.4 − 5) = 18.1 workable days per month. The job takes 120 / 18.1 = 6.6 months, or 201 calendar days, against 168 with no weather, and the normal weather costs 23.6 workdays. If 28 workdays are lost, the excess is 4.4 workdays.

Why it matters

The calculator helps schedulers, project managers, contractors and owners to put a realistic weather allowance in a schedule, to compare a bid duration with the climate and to document a delay claim with numbers.

Good to know

Use weather days of the right season, since a winter and a summer activity lose very different numbers of days, and run each phase on its own. Count the days against the limits of the activity from the specifications, and keep a daily log with the weather and the work done, because a claim depends on records. Remember that most contracts give a time extension only for weather worse than the normal for the period, and the notice and the proof rules apply. Weather on a non-critical activity may cost no time at all if there is float, so check the critical path before you claim.

The slack time calculator gives the float of an activity, the earned value calculator tracks the schedule and the cost, the cold weather concrete calculator checks the cooling of a pour and the concrete evaporation calculator checks hot weather.

Frequently asked questions

What is a workable day?

A workable day is a calendar day on which the crew can work on the activity. A day is lost if it is a weekend or a holiday, or if the weather stops the work: rain above a limit, wind for crane lifts, frost for concrete and masonry, or extreme heat. The weather days that count depend on the activity and are set in the schedule.

How do I find the normal weather days?

Use the climate records of a station close to the site, for example the normals of the national weather service, and count the days per month that go over the limit of the activity, such as 0.1 inch of rain or a low temperature. Many contracts name the number of days per month to expect, and only the days beyond that number justify a time extension.

Why is the weather day multiplied by the work week?

A day of rain on a Sunday on a five day week costs nothing, so only the share of weather days that fall on a working day is lost. The calculator multiplies the weather days by the working days per week over seven. It assumes weather days are spread evenly through the week.

What does the calculator leave out?

The calculator leaves out the days that the site needs to dry after a storm, the effect of a critical path with float, the productivity lost on a day of poor weather in which work goes on, the seasonal change from month to month and the rules of the contract on notice and documentation. For a long job, run the calculator for each season.