The pothole patch asphalt calculator gives the area patched, the volume of the patches, the tons of asphalt mix to order and the crew hours of a pothole repair program, from the number and the size of the potholes, the depth and the density of the mix.
How the calculation works
- Enter the number of potholes, their average diameter and the depth of the patch.
- Enter the density of the compacted mix, the compaction and waste allowance and the crew production.
- The calculator finds the area patched, the volume, the asphalt mix to order and the crew hours.
Example
A program of 120 potholes with an average diameter of 1.5 ft patches 120 × 0.7854 × 1.5² = 212 ft². With a patch 4 in deep, the volume is 212.06 × 4 / 12 = 70.7 ft³. The compacted mix weighs 145 pcf, so with a 15 % allowance the order is 70.69 × 145 / 2,000 × 1.15 = 5.89 tons. A crew that makes 6 patches/h needs 120 / 6 = 20.0 h.
Why it matters
The calculator helps public works crews, road maintenance supervisors, contractors and students to order the right tonnage of asphalt for a repair program, to plan the crew hours after a winter, and to compare the quantity of mix of several depths or sizes of patches.
Good to know
Cut the edges of the pothole square and vertical, clean it and let it dry, then tack the sides and the bottom. Place the mix in layers of 3 in or less, compact each layer with a plate compactor or a roller, and leave the patch slightly high. Keep the mix at the right temperature and order only what the crew can place before it cools.