Compaction roller calculator: production and number of rollers for a compacted lift

Enter the drum width, the speed, the lift thickness, the number of passes, the efficiency and the placement rate to get the area per hour, the compacted production and the number of rollers.

Updated on
Your inputs
ft

Value out of range

mph

Value out of range

in

Value out of range

Value out of range

Value out of range

yd³/h

Value out of range

Results

Production, compacted volume

304.2 yd³/h

Area compacted per hour
12,320 ft²/h
Rollers needed (theoretical)
2.30
Rollers to use
3

The compaction roller calculator gives the area compacted per hour, the production in compacted volume and the number of rollers needed for a fill, a subgrade or a base course, from the width of the drum, the speed, the lift thickness, the number of passes and the efficiency.

How the calculation works

  • Enter the effective width of the drum, the speed of the roller and the thickness of the compacted lift.
  • Enter the number of passes required by the specification, the efficiency and the required placement rate.
  • The calculator finds the area compacted per hour, the production in compacted volume and the number of rollers needed.

Example

A roller with a drum of 7 ft travels at 2.5 mph and makes 6 passes on a lift of 8 in, with an efficiency of 0.8. The area compacted per hour is 7 × 2.5 × 5,280 / 6 × 0.8 = 12,320 ft²/h. The compacted volume is 12,320 × 8 / 12 / 27 = 304.2 yd³/h. For a placement rate of 700 yd³/h, the number of rollers is 700 / 304.2 = 2.30, so 3 rollers are used.

Why it matters

The calculator helps earthwork contractors, estimators, quality control engineers and students to match the compaction to the production of the spreading, to plan the number of rollers for a pavement or an embankment, and to see how the lift thickness and the passes change the output.

Good to know

Run a test strip at the start of the job to find the number of passes and the moisture that give the specified density, and keep the lift thickness within the limit of the roller. Overlap the passes by 6 to 12 in, keep the speed constant, and plan a roller for each spreading unit so that the compaction does not become the bottleneck of the job.

The soil compaction calculator checks the density and the moisture, the earthwork swell and shrink calculator converts the volumes, the CBR subgrade modulus calculator rates the subgrade and the excavation calculator gives the volume to place.

Frequently asked questions

How is the production of a roller calculated?

The area compacted per hour is the width of the drum times the speed times the efficiency, divided by the number of passes. The compacted volume is this area times the thickness of the lift. In US units, the production in compacted cubic yards per hour is the width in feet times the speed in mph times the lift in inches times 16.3, divided by the number of passes, times the efficiency.

How many passes are needed?

The number of passes depends on the soil, the type and the weight of the roller, the thickness of the lift and the moisture, and it is found from a test strip before the work. A typical value is 4 to 8 passes for a granular fill with a vibratory roller, and a cohesive soil with a sheepsfoot roller may need 6 to 10 passes. More passes beyond the optimum do not increase the density and can break the material.

What are the usual speeds and efficiencies?

A vibratory smooth drum roller works at about 1.5 to 3 mph (2.5 to 5 km/h), and a pneumatic roller at 3 to 5 mph (5 to 8 km/h). The efficiency of 0.75 to 0.85 takes into account the overlap of the passes, the turns, the waiting and the stops. The width used is the effective width, which is less than the width of the drum by the overlap of about 6 in (15 cm).

What are the limits of the calculator?

The calculator gives a steady production for a given number of passes. It does not include the time to water or to dry the soil, the spreading and the grading of the material, the number of passes needed at the edges, the roller that waits for the trucks or the effect of the moisture on the density. The density must be checked by the tests of the project, and the roller pattern adjusted to the results.