Slipform curb and gutter production calculator: concrete, trucks and time

Enter the length, the section, the machine speed, the efficiency, the allowance, the truck capacity and the hours to get the concrete, the truck loads, the production rate and the time.

Updated on
Your inputs
ft

Value out of range

ft²

Value out of range

ft/min

Value out of range

Value out of range

%

Value out of range

yd³

Value out of range

h

Value out of range

Results

Paving time

11.9 h

Concrete to order
175.0 yd³
Truck loads
18
Production rate
14.0 yd³/h
Working days
1.49 days

The slipform curb and gutter production calculator gives the concrete to order, the number of truck loads, the production rate, the paving time and the working days of a curb and gutter job, from the length, the section and the speed of the machine.

How the calculation works

  • Enter the length of curb and gutter and the cross-section area of the profile.
  • Enter the machine speed, the job efficiency, the waste allowance, the truck capacity and the hours per day.
  • The calculator finds the concrete to order, the truck loads, the production rate, the paving time and the working days.

Example

A slipform machine places 3,000 ft of curb and gutter with a section of 1.5 ft², so the volume is 1.5 × 3,000 / 27 = 166.7 yd³, or 175.0 yd³ with a 5 % allowance. With trucks of 10 yd³, that is 18 loads. At 6 ft/min and an efficiency of 0.7, the production is 1.5 × 6 × 60 × 0.7 / 27 = 14.0 yd³/h, and the paving takes 3,000 / (6 × 60 × 0.7) = 11.9 h, or 1.49 days of 8 h.

Why it matters

The calculator helps paving contractors, estimators, inspectors and students to plan the concrete supply of a curb and gutter job, to check how many trucks per hour the machine needs, and to estimate the number of days of the crew from the length and the speed.

Good to know

Keep a constant supply of concrete with a uniform slump, because a stop of the machine leaves a mark in the curb. Set the string line carefully, and check the grade and the alignment before the work. Cure the curb at once and cut the joints in due time, and protect the fresh concrete against the rain and the hot sun.

The ready-mix truck fleet size calculator sizes the supply of concrete, the curb opening inlet capacity calculator checks the capacity of a curb inlet, the concrete volume calculator gives the volume of other shapes and the concrete evaporation rate calculator warns of the plastic cracking.

Frequently asked questions

What is a slipform curb machine?

A slipform curb machine is a paver that extrudes the concrete of a curb, a gutter or a curb and gutter through a mold while it moves forward along a string line or a guide. The concrete is fed in a hopper, vibrated in the mold and left in shape without any form on the sides. It places curbs much faster than the hand forming and with a more uniform finish.

How is the concrete volume found?

The volume is the cross-section area of the profile times the length of the curb. A common profile of curb and gutter has a section of about 1.5 ft², or 0.14 m², and the area depends on the height of the curb, the width of the gutter and its thickness. The volume has an allowance for the waste, the loss at the ends and the concrete left in the hopper and in the truck.

What is the production rate?

The production rate is the section area times the speed of the machine, times the efficiency of the job. The speed of the machine is limited by the slump of the concrete, the supply of trucks and the finish. The efficiency takes into account the stops for the trucks, the joints, the moves and the repairs. A rate of 0.7 is reasonable for a job with a good supply of concrete.

What are the limits of the calculator?

The calculator gives the quantities and the time of the paving for a constant section and a constant speed. It does not include the preparation of the base and the string line, the cutting of the joints, the finishing by hand at the corners and the driveways, the curing, the extra concrete for the radius of the curves or the delay when the concrete trucks do not arrive on time. The number of trucks per hour must follow the production rate.