The underpinning pit sequence and concrete calculator gives the number of pits, the number of passes, the pits per pass and the concrete volume to underpin a wall by the pit method, from the length of the wall, the size of a pit and the maximum length undermined at one time.
How the calculation works
- Enter the length of the wall, and the width, the depth and the breadth of one pit.
- Enter the maximum part of the wall that can be undermined at one time and the overbreak.
- The calculator finds the number of pits, the passes, the pits per pass and the concrete.
Example
A wall of 60 ft is underpinned with pits of 4 ft × 3 ft × 4 ft, which makes 60 / 4 = 15 pits. With 25 % of the wall undermined at the most, each pass has ceil(15 × 0.25) = 4 pits and the work takes 4 passes. One pit takes 48 / 27 = 1.78 yd³ of concrete, and with 10 % of overbreak the 15 pits take 29.33 yd³.
Why it matters
The calculator helps foundation contractors, structural engineers, estimators and students to plan the sequence of an underpinning, to estimate the concrete and to see how the limit on the length undermined changes the number of passes and the duration of the work.
Good to know
Dig the pits in the sequence of the engineer, never in two neighboring pits at the same time, and shore the sides of each pit. Place the concrete the same day, pack the last gap under the old footing with a dry mortar, and wait for the strength before digging the next pass. Watch the cracks and the level of the wall during the work.