Wheel loader calculator: hourly production of a front-end loader

Enter the bucket size, the fill factor, the fixed time, the travel distance, the speed, the efficiency, the swell and the truck size to get the cycle, the production and the truck loading time.

Updated on
Your inputs
yd³

Value out of range

Value out of range

min

Value out of range

ft

Value out of range

mph

Value out of range

min

Value out of range

%

Value out of range

yd³

Value out of range

Results

Production, bank volume

169 yd³/h

Cycle time
0.85 min
Cycles per hour
58.5
Production, loose volume
211 yd³/h
Time to load one truck
3.4 min

The wheel loader calculator gives the cycle time, the cycles per hour, the production in loose and bank volume and the time to load one truck of a front-end loader, from the bucket capacity, the fill factor, the fixed time, the travel distance and the speed.

How the calculation works

  • Enter the bucket capacity, the fill factor and the fixed time of the loading cycle.
  • Enter the travel distance between the pile and the hopper or the truck, the average speed, the working time per hour, the swell and the truck capacity.
  • The calculator finds the cycle time, the cycles per hour, the production in loose and bank volume and the time to load one truck.

Example

A loader with a bucket of 4 yd³ has a fill factor of 0.9, a fixed time of 0.40 min and travels 100 ft each way at 5 mph (440 ft/min). The cycle is 0.40 + 2 × 100 / 440 = 0.85 min. With 50 min of work per hour, there are 58.5 cycles per hour. The loose production is 4 × 0.9 × 58.5 = 211 yd³/h. With a swell of 25 %, the bank production is 169 yd³/h, and a truck of 12 yd³ is loaded in 3.4 min.

Why it matters

The calculator helps earthwork and quarry contractors, estimators, equipment planners and students to estimate the output of a loader that feeds trucks or a hopper, to compare a short and a long travel and to size the number of trucks that the loader can load.

Good to know

Position the truck and the pile so that the loader travels a short and level distance, with a V-pattern. Use the bucket that fits the material and the truck, so that a truck is filled with a whole number of buckets, usually three to five. Keep the haul road clean and level, and use the real cycle times that you measure on the job for the final estimate.

The excavator productivity calculator estimates a hydraulic excavator, the dozer production calculator estimates a blade push, the earthwork swell and shrink calculator converts the volumes and the labor productivity calculator gives the work output of the crew.

Frequently asked questions

How is the production of a wheel loader calculated?

The production is the load of the bucket times the number of cycles per hour. The cycle includes the fixed time, which is the loading of the bucket, the maneuvers and the dumping, and the travel time between the pile and the truck or the hopper. The load is the capacity of the bucket times the fill factor, and the number of cycles is the working minutes per hour divided by the cycle time.

What is the fixed time of a loader?

The fixed time of a loader is typically 0.35 to 0.5 minutes for a V-pattern loading of a truck, with the loading of the bucket, the reverse, the turn, the raise and the dump. It depends on the material, the skill of the operator and the layout of the pile and of the truck. A good layout, with a short and level approach, reduces the fixed time and the wear of the tires.

Why are the loose and the bank volumes different?

The bucket of a loader carries loose material. Soil dug from the bank occupies more volume when it is loose, according to the swell, so the production in bank volume is the loose production divided by one plus the swell. The bank volume is the one used for the quantities of the earthwork and for the payment.

What are the limits of the calculator?

The calculator uses a constant travel speed and a steady cycle. It does not include the acceleration, the grade, the soft ground that slows the machine, the waiting for the trucks, the rehandling of the pile or the dozer that feeds the loader. The matching of the number of trucks with the loader is a separate analysis, and the real cycle times of the job should be measured.