The scraper production calculator gives the cycle time, the trips per hour, the loose and bank production and the hours needed for a job of scraper haul, from the capacity of the bowl, the fill factor, the distances and the speeds.
How the calculation works
- Enter the bowl capacity, the fill factor, the haul and return distances and the speeds loaded and empty.
- Enter the load, maneuver and dump time, the working minutes per hour, the swell of the soil and the job volume.
- The calculator finds the cycle time, the trips per hour, the loose and bank production and the hours for the job.
Example
A scraper with a bowl of 24 yd³ and a fill factor of 0.9 hauls 3,000 ft loaded at 15 mph (2.27 min) and returns 3,000 ft empty at 20 mph (1.70 min). With 2.0 min to load, maneuver and dump, the cycle is 5.98 min. In a 50 min hour, that makes 8.37 trips, or 24 × 0.9 × 8.37 = 180.7 yd³/h loose. With 25 % swell, the bank production is 144.5 yd³/h, and a job of 50,000 yd³ takes 346 h.
Why it matters
The calculator helps earthwork contractors, estimators and students to estimate the production of a scraper on a haul, to compare several haul distances or speeds, to find how many hours a scraper needs for a volume, and to choose between a scraper, a loader with trucks and a dozer push.
Good to know
Keep the haul road wide, smooth and well watered, and cut the grade where it is possible, because the speed of the loaded scraper depends on it. Load downhill with a push loader to get a full bowl in a short time. Use the average speeds measured on site if they are known, and add a margin of 10 to 20 % to the hours for the weather and the breakdowns.