When two projects compete for the same team, which one first? Cost of delay gives the key to the answer: how much value is lost for each week a job is not finished. Divided by the job size, it gives the WSJF, Weighted Shortest Job First, a score that puts valuable, urgent and small jobs at the front. This calculator scores two jobs side by side and shows which should go first.
How the calculation works
- Cost of delay = business value + time criticality + risk reduction or opportunity
- WSJF = cost of delay ÷ job size
- Each component is a relative score from 1 to 20, estimated with the team
Example
Job A has a business value of 13, a time criticality of 8 and a risk reduction of 5, and a size of 5: its cost of delay is 26 and its WSJF is 5.2. Job B scores 8, 13 and 3 with a size of 2: its cost of delay is 24 but its WSJF is 12. B goes first, since it is almost as valuable and much smaller.
Why it matters
Teams often choose by the loudest request or the biggest project. WSJF shows that the order of work changes the total value delivered, and that a smaller job with a similar cost of delay should go first. It also makes the trade-off explicit, so the discussion focuses on the numbers rather than on opinions.
Good to know
The scores are relative estimates, not money, and they depend on the team agreeing on a scale. Dependencies, capacity and strategy can override the ranking, and the method gives odd results when sizes are poorly estimated. Check close scores with a second method such as RICE. This tool is for education.