Skip to content
Omnikalc

Material hoist cycle time and capacity calculator for a building site

Enter the lift height, the speed, the loading time, the efficiency, the payload and the quantity of material to get the cycle time, the trips per hour, the throughput and the hours needed.

Updated on
Your inputs
ft

Value out of range

ft/min

Value out of range

s

Value out of range

%

Value out of range

lb

Value out of range

tons

Value out of range

Results

Hours to lift the material

2.50 h

One-way travel time
45 s
Cycle time
210 s
Trips per hour
13.7
Throughput
24.0 tons/h

The material hoist cycle time and capacity calculator gives the one-way travel time, the cycle time, the trips per hour, the throughput and the hours to lift the material for a construction hoist, from the height, the speed, the loading time, the efficiency and the payload.

How the calculation works

  • Enter the height of the lift, the speed of the hoist and the loading and unloading time.
  • Enter the operating efficiency, the payload per trip and the quantity of material to lift.
  • The calculator finds the cycle time, the trips per hour, the throughput and the hours needed.

Example

A hoist goes up 150 ft at 200 ft/min, which takes 45 s one way. With 120 s of loading and unloading, the cycle is 2 × 45 + 120 = 210 s. At 80 % efficiency, it makes 3,600 / 210 × 0.8 = 13.7 trips per hour. With 3,500 lb per trip, the throughput is 24.0 tons/h, so 60 tons of material take 2.50 h.

Why it matters

The calculator helps site managers, logistics planners, estimators and students to check if a hoist can move the materials of a building at the pace of the schedule, to see if the loading time or the speed is the limit, and to decide if a second hoist is needed.

Good to know

Plan the loading with the trades so that the car does not wait, use pallets and carts that fit the car, and schedule the deliveries outside the peak hours. Never exceed the rated load of the car, secure the load, and stop the hoist when the wind is above the limit of the manufacturer. Do an inspection of the hoist every day.

The tower crane calculator checks the load moment of a lift, the sling angle calculator gives the tension in the slings, the bucket elevator capacity calculator gives the capacity of a vertical conveyor and the escalator capacity calculator gives the capacity of a moving stair.

Frequently asked questions

What is a material hoist?

A material hoist, or construction hoist, is a lift fixed on the outside of a building under construction. It has a car which runs on a mast with a rack and pinion drive, and it carries materials, tools and sometimes workers up to the floors. It lets the site move the materials without the tower crane, which is then free for the heavy lifts.

How is the cycle time found?

The cycle time is the time of the trip up, plus the time of the trip down, plus the time of the loading and of the unloading. The travel time is the height divided by the speed of the hoist. The time of the loading depends on the way the materials are brought to the car and on the number of the workers at the ground and at the floors. It is often the largest part of the cycle.

What is the operating efficiency?

The operating efficiency is the part of the time when the hoist really works, because it waits for the loads, for a call at another floor, for the radio, for the wind or for the maintenance. A value of 70 to 85 % is common for a well organized site. A lower value shows that the loading is the bottleneck, and the hoist is then not the limit.

What are the limits of the calculator?

The calculator uses a single stop at the top and the average values. It does not take into account the stops at the intermediate floors, the acceleration and the slowing of the car, the limit of the wind, the waiting of the other trades, the difference between the loads of the up and down trips or the shifts of the day. The rated capacity of the hoist must never be exceeded.