The railroad track materials calculator gives the number of ties, the weight of rail, the volume and weight of ballast and the tie plates for a length of track, from the tie spacing, the weight of the rail and the section of the ballast.
How the calculation works
- Enter the length of track, the tie spacing, the weight of the rail and the length of the ties.
- Enter the ballast section: shoulder, depth, side slope and bulk density.
- The calculator finds the number of ties, the weight of rail, the volume and weight of ballast and the tie plates.
Example
A track of 2.5 mi with ties every 19.5 in. needs 2.5 × 63,360 / 19.5 = 8,123.1, rounded up to 8,124 ties, and 16,248 tie plates. Two rails of 115 lb/yd weigh 2.5 × 1,760 × 2 × 115 / 2,000 = 506 tons. A ballast section of ties of 8.5 ft with a 1 ft shoulder, a depth of 1 ft and a slope of 2 to 1 has an area of 12.5 ft², so the track needs 6,111 yd³, that is 8,250 tons of ballast at 100 lb/ft³.
Why it matters
The calculator helps railroad engineers, track contractors, industrial rail owners, estimators and students to list the main materials of a track project, to compare the effect of the tie spacing and the ballast section, and to plan the delivery and the hauling.
Good to know
Use the standard of the owner for the tie spacing, the rail and the ballast section, and add the waste to the quantities: 5 percent for ties and plates, and 10 percent for the ballast, which also compacts under traffic. Order the ballast by weight from a quarry and check its gradation. Use the bulk density from the quarry and not the generic 100 lb/ft³.
Related tools
The gravel driveway calculator gives the stone for a road, the geogrid base reinforcement calculator gives the rolls of geogrid, the dump truck loads calculator gives the loads to haul the ballast and the compaction roller production calculator gives the area compacted per hour.