Shear stud calculator: number of headed studs on a composite beam

Enter the stud size, the concrete and steel strengths, the slab width and thickness, the beam area and span and the degree of composite action to get the stud strength, the shear and the studs.

Updated on
Your inputs
ksi

Value out of range

ksi

Value out of range

Value out of range

in

Value out of range

in

Value out of range

in²

Value out of range

ksi

Value out of range

ft

Value out of range

%

Value out of range

Results

Studs on the beam

48

Strength of one stud
21.5 kip
Horizontal shear for full composite action
515 kip
Studs per half span
24
Average spacing of the studs
7.5 in

The shear stud calculator gives the strength of one stud, the horizontal shear, the studs per half span, the total number of studs and their average spacing for a composite steel beam with a concrete slab, from the stud size, the materials and the section.

How the calculation works

  • Enter the stud diameter, the concrete strength, the stud tensile strength and the Rg × Rp factor.
  • Enter the effective slab width, the concrete thickness, the steel area and yield strength of the beam, the span and the degree of composite action.
  • The calculator finds the strength of one stud, the horizontal shear, the studs per half span, the total studs and their average spacing.

Example

A 3/4 in stud in 4 ksi concrete has an area of 0.442 in² and a strength of the smaller of 0.5 × 0.442 × √(4 × 3,605) = 26.5 kip and 0.75 × 0.442 × 65 = 21.5 kip, that is 21.5 kip. The slab, 90 in wide and 3.25 in thick, can give 994.5 kip, and the beam, with 10.3 in² at 50 ksi, gives 515 kip, so the horizontal shear is 515 kip. For full composite action, each half of the 30 ft span needs ceil(515 / 21.5) = 24 studs, that is 48 studs with an average spacing of 7.5 in.

Why it matters

The calculator helps structural engineers, detailers, estimators and students to estimate the number of headed studs of a composite floor, to see how the degree of composite action and the deck change the studs, and to price the welding of the studs for a job.

Good to know

Weld the studs through clean and dry deck with the right equipment and test the first studs of the day with a bend test. Place them in the center of the rib or at the position given by the drawings, and do not exceed the spacing limits. Check the studs of the beam ends on the drawings, because the studs are denser where the shear is the highest.

The steel beam lateral-torsional buckling calculator checks the bare beam, the beam camber for dead load calculator gives the camber, the one-way slab minimum thickness calculator gives the slab thickness and the bolt shear capacity calculator checks the bolts of a connection.

Frequently asked questions

What is a shear stud?

A shear stud is a steel bar with a head, welded to the top flange of a steel beam through the metal deck, that connects the beam to the concrete slab. The studs carry the horizontal shear between the two materials, so that they work together as a composite beam. A composite beam is stiffer and stronger than the steel beam alone, and it can use a lighter section.

How is the strength of a stud found?

In the specification AISC 360, the strength of a stud is the smaller of two values. The first is 0.5 times the area of the stud times the square root of the concrete strength times its modulus, which is the crushing of the concrete around the stud. The second is the group and position factor times the area times the tensile strength of the stud, which is the failure of the steel. The metal deck reduces the strength with the factor Rg × Rp.

How many studs are needed?

The horizontal shear to transfer for full composite action is the smaller of the strength of the concrete slab, 0.85 f'c times the effective area, and the strength of the steel section, its area times its yield strength. This shear is divided by the strength of one stud to get the studs between the point of maximum moment and the end of the beam. A partial composite action uses a fraction of this shear and fewer studs.

What are the limits of the calculator?

The calculator gives the number of studs for a simply supported beam under a uniform load, with the shear computed at the maximum moment. It does not check the minimum spacing of six diameters along the beam, the maximum spacing, the edge distance, the rib geometry of the deck, the concentrated loads, the shored construction or the minimum degree of composite action, which is 25 % in the specification. The final design belongs to the engineer.

Was this calculator helpful?

Thanks for your feedback!

Results are estimates provided for information purposes. They do not replace professional advice.