The concrete saw cut joint calculator gives the ratio of the joint spacing to the thickness, the number of joints, the total saw cut length, the depth of the cut and the sawing time for a concrete slab, from its size, its thickness and the joint spacing.
How the calculation works
- Enter the length, the width and the thickness of the slab, and the joint spacing.
- Choose the depth of the saw cut and enter the sawing speed.
- The calculator finds the ratio of the spacing to the thickness, the number of joints, the total saw cut length, the depth and the sawing time.
Example
A slab 100 ft long and 60 ft wide is 6 in thick, with joints every 12 ft, a ratio of 12 × 12 / 6 = 24.0. It has ceil(100 / 12) − 1 = 8 joints across the width of 60 ft and ceil(60 / 12) − 1 = 4 joints along the length of 100 ft, that is 12 joints and 8 × 60 + 4 × 100 = 880 ft of saw cut. The depth is 1/4 of 6 in, or 1.5 in, and at 200 ft/h the sawing takes 4.4 h.
Why it matters
The calculator helps concrete contractors, floor designers, estimators and students to check the spacing of the control joints of a slab, to estimate the length to saw and the time of the saw crew, and to see how the joint spacing changes the number of joints and the cost of the sawing and sealing.
Good to know
Cut the joints as soon as the concrete can bear the saw without raveling, usually 4 to 12 hours after the finishing, and cut all the joints before the slab cracks. Keep the panels square or with a ratio of the sides lower than 1.5, and extend the joints to the columns and the re-entrant corners. Seal the joints later, when most of the shrinkage has occurred.
Related tools
The slab joint spacing calculator gives the maximum spacing from the rules of the practice, the joint sealant movement and width calculator sizes the sealant, the concrete crack width calculator checks the cracks of a reinforced member and the concrete evaporation rate calculator warns of the plastic cracking in the hot and windy weather.