The tremie seal calculator gives the uplift pressure, the resisting pressure, the factor of safety, the thickness needed and the concrete volume of an underwater concrete seal at the bottom of a cofferdam, from the water head, the thickness and the bond.
How the calculation works
- Enter the water head on the underside of the seal, the thickness placed and the unit weight of the underwater concrete.
- Enter the bond and friction of the walls and the piles, the area of the seal and the required factor of safety.
- The calculator finds the uplift pressure, the resisting pressure, the factor of safety, the thickness needed and the volume of the seal.
Example
A tremie seal has a water head of 20 ft on its underside, so the uplift is 62.4 × 20 = 1,248 psf. The seal is 10 ft thick and the concrete weighs 145 pcf, with a bond of 150 psf, so the resistance is 145 × 10 + 150 = 1,600 psf and the factor of safety is 1.28. For a required factor of 1.2, the thickness needed is (1.2 × 1,248 − 150) / 145 = 9.29 ft, a ratio of 0.93. The volume of a seal of 900 ft² is 333.3 yd³.
Why it matters
The calculator helps bridge and marine engineers, contractors and students to check if a tremie seal is thick enough to resist the uplift once the cofferdam is dewatered, to find the thickness for a given factor of safety, and to estimate the volume of concrete to order for the pour.
Good to know
Keep the tremie pipe embedded in the fresh concrete by at least 3 ft, 1 m, at all times, and fill the pipe with a plug so that the first concrete does not mix with the water. Use a concrete with a slump of 6 to 8 in, a high cement content and a retarder. Clean the laitance after the cure, and check the seal with the divers or the cores before the dewatering.
Related tools
The buried tank flotation calculator checks a structure against the uplift of the groundwater, the mass concrete temperature calculator checks the heat of a large pour, the ready-mix truck fleet size calculator sizes the supply of concrete and the trench dewatering calculator sizes the pumping of an excavation.