The water main flushing calculator gives the flow needed, the pipe volume, the flushing time, the total water to discharge and the ratio to the available flow for a new water main, from the diameter, the length, the flushing velocity and the number of volume changes.
How the calculation works
- Enter the inside diameter and the length of the pipe to flush.
- Enter the flushing velocity, the number of pipe volume changes and the flow available at the hydrant.
- The calculator finds the flow needed, the pipe volume, the flushing time, the total water and the ratio to the available flow.
Example
A 12 in main has a section of 0.785 ft². At 2.5 ft/s, the flow needed is 2.5 × 0.785 × 448.8 = 881 gpm. The 2,000 ft of pipe hold 11,750 gal. For 3 volume changes, the flushing takes 3 × 2,000 / 2.5 / 60 = 40.0 min and discharges 35,251 gal. A hydrant that gives 1,000 gpm is enough, with a ratio of 0.88.
Why it matters
The calculator helps water utility crews, contractors, inspectors and students to plan the flushing of a new main, to check if a hydrant gives enough flow for the velocity needed, and to estimate the time of the flushing and the volume of water to discharge or to haul.
Good to know
Open the hydrant or the blow-off slowly to avoid a pressure surge, and flush from the clean end toward the dirty end. Keep a hose or a pipe to carry the water to a safe place, and dechlorinate or filter the water when it is required. Continue until the water is clear, and then take the samples for the bacteriological tests.
Related tools
The water main disinfection chlorine dose calculator gives the chlorine for the next step, the pipe test leakage allowance calculator checks the pressure test, the hydrostatic test pressure calculator gives the test pressure and the trench pipe laying production calculator plans the laying of the pipe.